Power management mechanism for data storage environment

  • US 10,001,826 B2
  • Filed: 01/15/2009
  • Issued: 06/19/2018
  • Est. Priority Date: 01/15/2009
  • Status: Active Grant
First Claim
Patent Images

1. A method for facilitating power instability in a central electronics complex (CEC) of data storage computing environment in advance of a potential power failure, comprising:

  • upon receipt of a first early power off warning (EPOW) signal indicating an input electrical power instability has been detected in the CEC, decreasing a first priority of execution of a first data storage task to be performed pursuant to a new data storage request thereby delaying acceptance of the new data storage request to a limit of protocol used for conveying the new data storage request, while increasing a second priority of execution of a second data storage task to destage data in nonvolatile storage (NVS) to disk;

    upon the passage of at least a predetermined threshold of time comprising no less than 30 seconds subsequent to the first EPOW thereby allowing a timeframe for the decreasing the first priority and increasing the second priority wherein a complete destaging of all the data in the NVS to the disk is attempted, and upon receipt of a second EPOW signal indicating power failure, executing a system shutdown procedure; and

    while decreasing the first priority and increasing the second priority upon receipt of the first EPOW such that the power failure has not yet occurred, monitoring execution of the second data storage task and additional data storage tasks to destage the data in NVS to the disk in view of a battery capacity time for performing the system shutdown procedure, wherein if the second and additional data storage tasks are not able to be completed within the battery capacity time as monitored during the decreasing of the first priority and increasing the second priority, the system shutdown procedure comprising a fire hose dump (FHD) procedure is immediately executed regardless of whether the second EPOW has been received.

View all claims
  • 1 Assignment
Timeline View
Assignment View
    ×
    ×