System tools for integrating individual load forecasts into a composite load forecast to present a comprehensive, synchronized and harmonized load forecast
First Claim
Patent Images
1. A system, comprising:
- a memory that stores executable instructions; and
a processor, coupled to the memory, that executes or facilitates execution of the executable instructions to at least;
integrate at least two load forecasts associated with a power grid center into a composite load forecast for the power grid center;
generate scheduling data for a device of the power grid center based on the composite load forecast, other scheduling data for the power grid center that is determined by a first forecast engine associated with the at least two load forecasts, timing data for at least one power generator of the power grid center that is determined by a second forecast engine associated with the at least two load forecasts, and financial data for the power grid center that is determined by a third forecast engine associated with the at least two load forecasts, wherein the first forecast engine is associated with a first time range, the second forecast engine is associated with a second time range, and the third forecast engine is associated with a third time range; and
manage power provided to the device of the power grid center based on the scheduling data.
2 Assignments
0 Petitions
Accused Products
Abstract
A system tool merges different load forecasts for power grid centers. A plurality of load forecast engines are coupled to a load forecast interface and a relational data base that saves load forecast engine data as an input through the load forecast interface. A comprehensive operating plan is coupled to the load forecast engines and the relational database. The comprehensive operating plan is configured to integrate individual load forecasts into a composite load forecast to present a comprehensive, synchronized and harmonized load forecast. A program interface provides access to the composite load forecasting schedule.
182 Citations
20 Claims
-
1. A system, comprising:
-
a memory that stores executable instructions; and a processor, coupled to the memory, that executes or facilitates execution of the executable instructions to at least; integrate at least two load forecasts associated with a power grid center into a composite load forecast for the power grid center; generate scheduling data for a device of the power grid center based on the composite load forecast, other scheduling data for the power grid center that is determined by a first forecast engine associated with the at least two load forecasts, timing data for at least one power generator of the power grid center that is determined by a second forecast engine associated with the at least two load forecasts, and financial data for the power grid center that is determined by a third forecast engine associated with the at least two load forecasts, wherein the first forecast engine is associated with a first time range, the second forecast engine is associated with a second time range, and the third forecast engine is associated with a third time range; and manage power provided to the device of the power grid center based on the scheduling data. - View Dependent Claims (2, 3, 4, 5, 6, 7)
-
-
8. A computer readable storage device comprising computer-executable instructions that, in response to execution, cause an apparatus comprising a processor, to perform operations, comprising:
-
combining a first load forecast associated with a power grid center and a second load forecast associated with the power grid center into a combined load forecast for the power grid center; generating operating data for a device of the power grid center based on the combined load forecast, scheduling data for the power grid center that is determined by a first forecast engine associated with a first interval of time, timing data for at least one power generator of the power grid center that is determined by a second forecast engine associated with a second interval of time, and financial data for the power grid center that is determined by a third forecast engine associated with a third interval of time; and managing power provided to the device of the power grid center based on the operating data. - View Dependent Claims (9, 10, 11, 12, 13, 14)
-
-
15. A method, comprising:
-
merging, by a system comprising a processor, a plurality of load forecasts associated with a power grid center into a load forecast for the power grid center; generating, by the system, scheduling data for a device of the power grid center based on the load forecast, daily scheduling data for the power grid center that is determined by a first forecast engine associated with a first time period and the plurality of load forecasts, timing data for at least one power generator of the power grid center that is determined by a second forecast engine associated with a second time period and the plurality of load forecasts, and financial data for the power grid center that is determined by a third forecast engine associated with a third time period and the plurality of load forecasts; and managing, by the system, an amount of energy provided to the device of the power grid center during a period of time based on the scheduling data. - View Dependent Claims (16, 17, 18, 19, 20)
-
Specification