Mechanism to extend the peak power capability of a mobile platform
First Claim
Patent Images
1. An apparatus comprising:
- voltage monitoring hardware to monitor voltage being supplied by a battery to a system load;
an energy storage coupled to the voltage monitoring hardware to supplement supply of power to the system load when the voltage supplied to the system load by the battery, as monitored by the voltage monitoring hardware, drops below a first threshold voltage level, the first threshold voltage level being above a minimum voltage level associated with the system; and
a battery charger to charge the battery that is to supply power to the system load and to charge the energy storage when the battery is supplying the power to the system load and the voltage being supplied by the battery to the system load is above a second threshold voltage level that is higher than the first threshold voltage level and does not charge the energy storage when the voltage being supplied by the battery to the system load is below the second threshold voltage level but higher than the first threshold voltage level, the voltage monitoring hardware being operable to monitor the voltage supplied by the battery to the system load after the voltage drops below the second threshold voltage level.
1 Assignment
0 Petitions
Accused Products
Abstract
A method and apparatus for extending peak power capability of a computing device. In one embodiment, the apparatus comprises: voltage monitoring hardware to monitor voltage being supplied by a battery to a system load; and an energy storage coupled to the voltage monitoring hardware and/or charging scheme to supplement supply of power to the system load when the voltage supplied to the system load by the battery, as monitored by the voltage monitoring hardware, drops below a first threshold voltage level, the first threshold voltage level being above a minimum voltage level associated with the computing system.
10 Citations
23 Claims
-
1. An apparatus comprising:
-
voltage monitoring hardware to monitor voltage being supplied by a battery to a system load; an energy storage coupled to the voltage monitoring hardware to supplement supply of power to the system load when the voltage supplied to the system load by the battery, as monitored by the voltage monitoring hardware, drops below a first threshold voltage level, the first threshold voltage level being above a minimum voltage level associated with the system; and a battery charger to charge the battery that is to supply power to the system load and to charge the energy storage when the battery is supplying the power to the system load and the voltage being supplied by the battery to the system load is above a second threshold voltage level that is higher than the first threshold voltage level and does not charge the energy storage when the voltage being supplied by the battery to the system load is below the second threshold voltage level but higher than the first threshold voltage level, the voltage monitoring hardware being operable to monitor the voltage supplied by the battery to the system load after the voltage drops below the second threshold voltage level. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10)
-
-
11. A non-transitory machine-readable medium having stored thereon one or more instructions, which if performed by a machine causes the machine to perform a method comprising:
-
monitoring voltage supplied by a battery to a system load; and supplementing supply of power to the system load from an energy storage separate from the battery when the voltage supplied to the system load by the battery drops below a first threshold voltage level, the first threshold voltage level being above a minimum voltage level associated with system load and charging the energy storage when the voltage being supplied by the battery to the system load is above a second threshold voltage level which is above the first threshold voltage level, and further wherein supplementing supply of power to the system load from an energy storage occurs when the voltage being supplied by the battery to the system load is below the second threshold voltage level but higher than the first threshold voltage level. - View Dependent Claims (12, 13, 14, 15, 16, 17, 18, 19)
-
-
20. A method comprising:
-
monitoring voltage supplied by a battery to a system load; and supplementing supply of power to the system load from an energy storage separate from the battery when the voltage supplied to the system load by the battery drops below a first threshold voltage level, the first threshold voltage level being above a minimum voltage level associated with system load; and charging the energy storage when the voltage being supplied by the battery to the system load is above a second threshold voltage level which is above the first threshold voltage level, and further wherein supplementing supply of power to the system load from an energy storage occurs when the voltage being supplied by the battery to the system load is below the second threshold voltage level but higher than the first threshold voltage level. - View Dependent Claims (21, 22, 23)
-
Specification