Methods and systems for distributed power control of flexible datacenters
DCFirst Claim
1. A distributed power control system comprising:
- a flexible datacenter comprising;
(i) a plurality of computing systems powered by a behind-the-meter power input system,(ii) the behind-the-meter power input system configured to receive power from a power generation system prior to the power undergoing step-up transformation for transmission to the grid and deliver the power to the plurality of computing systems, and(iii) a datacenter control system configured to control the plurality of computing systems and the behind-the-meter power input system;
a remote master control system configured to issue instructions to the flexible datacenter that affect an amount of behind-the-meter power consumed by the flexible datacenter;
one or more processors; and
data storage comprising a first set of instructions that, when executed by the one or more processors, cause the datacenter control system to perform operations comprising;
receiving a first operational directive from the remote master control system, wherein the first operational directive is an operational directive for the flexible datacenter to ramp-down power consumption, andin response to receiving the first operational directive, causing the plurality of computing systems of the flexible datacenter to perform a first set of predetermined operations correlated with the first operational directive.
1 Assignment
Litigations
0 Petitions
Accused Products
Abstract
In an example embodiment, a distributed power control system can include a datacenter and a remote master control system. The datacenter can include (i) computing systems, (ii) a behind-the-meter power input system configured to receive power from a behind-the-meter power source and deliver power to the computing systems, and (iii) a datacenter control system configured to control the computing systems and the behind-the-meter power input system. The remote master control system can be configured to issue instructions to the datacenter that affect an amount of behind-the-meter power consumed by the datacenter. The datacenter control system can receive, from a local station control system configured to at least partially control the behind-the-meter power source, a directive for the datacenter to ramp-down power consumption, and in response to receiving the directive, cause the computing systems to perform a set of predetermined operations correlated with the directive.
81 Citations
20 Claims
-
1. A distributed power control system comprising:
-
a flexible datacenter comprising; (i) a plurality of computing systems powered by a behind-the-meter power input system, (ii) the behind-the-meter power input system configured to receive power from a power generation system prior to the power undergoing step-up transformation for transmission to the grid and deliver the power to the plurality of computing systems, and (iii) a datacenter control system configured to control the plurality of computing systems and the behind-the-meter power input system; a remote master control system configured to issue instructions to the flexible datacenter that affect an amount of behind-the-meter power consumed by the flexible datacenter; one or more processors; and data storage comprising a first set of instructions that, when executed by the one or more processors, cause the datacenter control system to perform operations comprising; receiving a first operational directive from the remote master control system, wherein the first operational directive is an operational directive for the flexible datacenter to ramp-down power consumption, and in response to receiving the first operational directive, causing the plurality of computing systems of the flexible datacenter to perform a first set of predetermined operations correlated with the first operational directive. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16)
-
-
17. A method performed by a datacenter control system of a flexible datacenter, wherein the flexible datacenter further comprises
(i) a plurality of computing systems powered by a behind-the-meter power input system and (ii) the behind-the-meter power input system configured to receive power from a power generation system prior to the power undergoing step-up transformation for transmission to the grid and deliver the power to the plurality of computing systems, wherein the datacenter control system is configured to control the plurality of computing systems and the behind-the-meter power input system, and wherein a remote master control system is configured to issue instructions to the flexible datacenter that affect an amount of behind-the-meter power consumed by the flexible datacenter, the method comprising: -
receiving a first operational directive from the remote master control system, wherein the first operational directive is an operational directive for the flexible datacenter to ramp-down power consumption; and in response to receiving the first operational directive, causing the plurality of computing systems of the flexible datacenter to perform a first set of predetermined operations correlated with the first operational directive. - View Dependent Claims (18)
-
-
19. A non-transitory computer readable medium having stored thereon instructions, that when executed by one or more processors of a datacenter control system of a flexible datacenter, cause the datacenter control system to perform operations comprising:
-
receiving a first operational directive from a remote master control system, wherein the remote master control system is configured to issue instructions to the flexible datacenter that affect an amount of behind-the-meter power consumed by the flexible datacenter, wherein the first operational directive is an operational directive for the flexible datacenter to ramp-down power consumption, wherein the flexible datacenter further comprises (i) a plurality of computing systems powered by a behind-the-meter power input system and (ii) the behind-the-meter power input system configured to receive power from a power generation system prior to the power undergoing step-up transformation for transmission to the grid and deliver power to the plurality of computing systems, and wherein the datacenter control system is configured to control the plurality of computing systems and the behind-the-meter power input system; and in response to receiving the first operational directive, causing the plurality of computing systems of the flexible datacenter to perform a first set of predetermined operations correlated with the first operational directive. - View Dependent Claims (20)
-
Specification