Power storage adapter for peak shift operation with a portable information handling system
First Claim
Patent Images
1. A power storage adapter (PSA), comprising:
- a PSA port;
a PSA battery; and
a PSA controller having access to memory media storing instructions executable by the PSA controller to;
receive, at a first time, an indication of a peak shift associated with an alternating current (AC) line power source, the indication specifying that the power storage adapter is to cease drawing electrical power from the AC line power source, the indication additionally indicating a further time period when an additional peak shift is to occur;
determine that a state of charge of the PSA battery is greater than a recharging state of charge;
in response to the indication and when the power storage adapter is electrically connected to the AC line power source, enter a peak shift by electrically disconnecting the power storage adapter from the AC line power source;
determine, after electrically disconnecting the power storage adapter from the AC line power source, that the state of charge of the PSA battery is less than the recharging state of charge, and in response, electrically connect the power storage adapter to the AC line power source;
in response to electrically connecting the power storage adapter to the AC line power source, terminate the peak shift of the AC line power source;
at a second time after terminating the peak shift of the AC line power source at the first time and during the further time period indicated by the previously received indication, entering the further peak shift of the AC line power source without receiving a further indication of the additional further peak shift associated with the AC line power source, including;
determine that the state of charge of the PSA battery is greater than the recharging state of charge; and
when the power storage adapter is electrically connected to the AC line power source, electrically disconnect the power storage adapter from the AC line power source.
7 Assignments
0 Petitions
Accused Products
Abstract
A power storage adapter may use a peak shift operation method when supplying electrical power from an AC line power source to a portable information handling system and the power storage adapter receives an indication of a peak shift associated with the AC line power source. In particular, the power storage adapter may cease drawing power from the AC line power source and begin supplying electrical power from a battery included with the power storage adapter to the portable information handling system.
-
Citations
20 Claims
-
1. A power storage adapter (PSA), comprising:
-
a PSA port; a PSA battery; and a PSA controller having access to memory media storing instructions executable by the PSA controller to; receive, at a first time, an indication of a peak shift associated with an alternating current (AC) line power source, the indication specifying that the power storage adapter is to cease drawing electrical power from the AC line power source, the indication additionally indicating a further time period when an additional peak shift is to occur; determine that a state of charge of the PSA battery is greater than a recharging state of charge; in response to the indication and when the power storage adapter is electrically connected to the AC line power source, enter a peak shift by electrically disconnecting the power storage adapter from the AC line power source; determine, after electrically disconnecting the power storage adapter from the AC line power source, that the state of charge of the PSA battery is less than the recharging state of charge, and in response, electrically connect the power storage adapter to the AC line power source; in response to electrically connecting the power storage adapter to the AC line power source, terminate the peak shift of the AC line power source; at a second time after terminating the peak shift of the AC line power source at the first time and during the further time period indicated by the previously received indication, entering the further peak shift of the AC line power source without receiving a further indication of the additional further peak shift associated with the AC line power source, including; determine that the state of charge of the PSA battery is greater than the recharging state of charge; and when the power storage adapter is electrically connected to the AC line power source, electrically disconnect the power storage adapter from the AC line power source. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10)
-
-
11. A method for peak shift operation, the method comprising:
-
receiving, at a first time and by a PSA controller of a power storage adapter, an indication of a peak shift associated with an AC line power source of the power storage adapter, the indication specifying that the power storage adapter is to cease drawing electrical power from the AC line power source, the indication additionally indicating a further time period when an additional peak shift is to occur; determining, by the PSA controller, that a state of charge of a PSA battery of the power storage adapter is greater than a recharging state of charge; in response to the indication and when the power storage adapter is electrically connected to the AC line power source, entering a peak shift by electrically disconnecting, by the PSA controller, the power storage adapter from the AC line power source; determining, after electrically disconnecting the power storage adapter from the AC line power source, that the state of charge of the PSA battery is less than the recharging state of charge, and in response, electrically connect the power storage adapter to the AC line power source; in response to electrically connecting the power storage adapter to the AC line power source, terminating the peak shift of the AC line power source; at a second time after terminating the peak shift of the AC line power source at the first time and during the further time period indicated by the previously received indication, entering the further peak shift of the AC line power source without receiving a further indication of the additional further peak shift associated with the AC line power source, including; determining that the state of charge of the PSA battery is greater than the recharging state of charge; and when the power storage adapter is electrically connected to the AC line power source, electrically disconnecting the power storage adapter from the AC line power source. - View Dependent Claims (12, 13, 14, 15, 16, 17, 18, 19, 20)
-
Specification