Dynamic work zone safety system and method
First Claim
1. A dynamic work zone safety system comprising:
- (a) a first traffic signalling device which is positioned along a roadside immediately upstream of a point where traffic is diverted to a single lane, said first traffic signalling device being defaulted to flash a suitable warning, “
DO NOT PASS”
or “
MERGE LEFT”
or “
MERGE RIGHT”
, thereby to provide a first “
NO PASSING”
or “
MERGE LEFT”
or “
MERGE RIGHT”
zone which is defined by the distance between said first traffic signalling device and the end of said work or construction zone;
(b) a second traffic signalling device which is positioned alongside a roadside a predetermined distance upstream of said first traffic signalling device, said second traffic signalling device being defaulted not to flash a suitable warning, “
DO NOT PASS”
or “
MERGE LEFT”
or “
MERGE RIGHT”
, but, when activated, flashes a suitable warning, “
DO NOT PASS”
or “
MERGE LEFT”
or “
MERGE RIGHT”
, thereby providing a second “
NO PASSING”
or “
MERGE LEFT”
or “
MERGE RIGHT”
zone which is contiguous to said first “
NO PASSING”
or “
MERGE LEFT”
or “
MERGE RIGHT”
zone, thereby to lengthen the “
NO PASSING”
or “
MERGE LEFT”
or “
MERGE RIGHT”
zone to between said second traffic signalling device and the end of said work or construction zone;
(c) a plurality of spaced-apart sensors along the roadway both downstream of, and upstream of, said second traffic signalling device, to detect and determine the length of a first traffic queue upstream of said first traffic signalling device between said first traffic signalling device and said second traffic signalling device, and to provide a first signal which is representative of the length of said first traffic queue; and
(d) a processor which are loaded with a suitable computer program for receiving said first traffic queue signal and for generating a first activation signal to activate said second traffic signalling device when said first traffic queue reaches a predetermined length, and for generating a first deactivation signal to deactivate said second traffic signal when said first traffic queue is less than said predetermined length;
thereby dynamically increasing or decreasing said “
NO PASSING”
or “
MERGE LEFT”
or “
MERGE RIGHT”
zone.
2 Assignments
0 Petitions
Accused Products
Abstract
A novel dynamic work zone safety system and method of traffic control for a construction work zone are provided herein. The system includes at least two traffic signalling device which are positioned along a roadside immediately upstream of a point where traffic is diverted to a single lane. The traffic signalling devices selectively flash a suitable warning, e.g., “DO NOT PASS” or “MERGE LEFT” or “MERGE RIGHT”, thereby to provide at least two “NO PASSING” or “MERGE LEFT” or “MERGE RIGHT” zones which is defined by the distance between the traffic signalling devices and the end of the work or construction zone. The “NO PASSING” or “MERGE LEFT” or “MERGE RIGHT” zones traffic signalling device and the end of the work or construction zone may thus be expanded or contracted. A plurality of spaced-apart sensors is disposed along the roadway both downstream of, and upstream of, the traffic signalling devices to detect and determine the length of traffic queues upstream of the traffic signalling devices, and provides signals which are representative of the length of the traffic queues. The processor receives the traffic queue signals and generates activation signals when the traffic queue reaches a predetermined length. It also generates a deactivation signal when the traffic queue is less than the predetermined length. This dynamically increases or decreases the “NO PASSING” or “MERGE LEFT” or “MERGE RIGHT” zone.
66 Citations
19 Claims
-
1. A dynamic work zone safety system comprising:
-
(a) a first traffic signalling device which is positioned along a roadside immediately upstream of a point where traffic is diverted to a single lane, said first traffic signalling device being defaulted to flash a suitable warning, “
DO NOT PASS”
or “
MERGE LEFT”
or “
MERGE RIGHT”
, thereby to provide a first “
NO PASSING”
or “
MERGE LEFT”
or “
MERGE RIGHT”
zone which is defined by the distance between said first traffic signalling device and the end of said work or construction zone;
(b) a second traffic signalling device which is positioned alongside a roadside a predetermined distance upstream of said first traffic signalling device, said second traffic signalling device being defaulted not to flash a suitable warning, “
DO NOT PASS”
or “
MERGE LEFT”
or “
MERGE RIGHT”
, but, when activated, flashes a suitable warning, “
DO NOT PASS”
or “
MERGE LEFT”
or “
MERGE RIGHT”
, thereby providing a second “
NO PASSING”
or “
MERGE LEFT”
or “
MERGE RIGHT”
zone which is contiguous to said first “
NO PASSING”
or “
MERGE LEFT”
or “
MERGE RIGHT”
zone, thereby to lengthen the “
NO PASSING”
or “
MERGE LEFT”
or “
MERGE RIGHT”
zone to between said second traffic signalling device and the end of said work or construction zone;
(c) a plurality of spaced-apart sensors along the roadway both downstream of, and upstream of, said second traffic signalling device, to detect and determine the length of a first traffic queue upstream of said first traffic signalling device between said first traffic signalling device and said second traffic signalling device, and to provide a first signal which is representative of the length of said first traffic queue; and
(d) a processor which are loaded with a suitable computer program for receiving said first traffic queue signal and for generating a first activation signal to activate said second traffic signalling device when said first traffic queue reaches a predetermined length, and for generating a first deactivation signal to deactivate said second traffic signal when said first traffic queue is less than said predetermined length;
thereby dynamically increasing or decreasing said “
NO PASSING”
or “
MERGE LEFT”
or “
MERGE RIGHT”
zone. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18)
-
-
19. A method of traffic control for a construction work zone that assists in the prevention of dangerous merging which occurs on the tapered approaches to work-zones which comprises:
-
(A) establishing a first “
NO PASSING”
or “
MERGE LEFT”
or “
MERGE RIGHT”
zone immediately upstream of said construction work zone;
(B) detecting and measuring traffic congestion at a plurality of locations approaching said first “
NO PASSING”
or “
MERGE LEFT”
or “
MERGE RIGHT”
zone as a first traffic queue; and
(C) determining, by means of software, the length of a “
NO PASSING”
or “
MERGE LEFT”
or “
MERGE RIGHT”
zone based on said detected traffic congestion, and based, on the length of said first traffic queue, automatically, by means of said software, expanding or shrinking said “
NO PASSING”
or “
MERGE LEFT”
or “
MERGE RIGHT”
zone upstream of said construction work zone appropriate for said measured level of traffic congestion.
-
Specification