Recalculating planned requests
First Claim
1. A method for scheduling work and delivery of material for items in a factory comprising:
- obtaining a customer order, the customer order including an item ordered by a customer, the item having an associated quantity of a material to produce;
determining a current state of an available inventory of material from a plurality of material sources;
generating a material request plan for producing the item using the customer order and the current state of the available inventory;
executing the material request plan, the executing the material request plan including netting deliveries of material with planned requests for material during the executing of the material request plan.
1 Assignment
0 Petitions
Accused Products
Abstract
A method for scheduling work and delivery of material for items in a factory which includes obtaining a customer order, determining a current state of an available inventory of material from a plurality of material sources, generating a material request plan for producing the item using the customer order and the current state of the available inventory, and executing the material request plan. The customer order includes an item, having an associated quantity of a material to produce, ordered by a customer. The executing the material request plan includes netting deliveries of material with planned requests for material during the executing of the material request plan.
22 Citations
39 Claims
-
1. A method for scheduling work and delivery of material for items in a factory comprising:
-
obtaining a customer order, the customer order including an item ordered by a customer, the item having an associated quantity of a material to produce;
determining a current state of an available inventory of material from a plurality of material sources;
generating a material request plan for producing the item using the customer order and the current state of the available inventory;
executing the material request plan, the executing the material request plan including netting deliveries of material with planned requests for material during the executing of the material request plan. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13)
-
-
14. A system for scheduling work and delivery of material for items in a factory comprising:
-
means for obtaining a customer order, the customer order including an item ordered by a customer, the item having an associated quantity of a material to produce;
means for determining a current state of an available inventory of material from a plurality of material sources;
means for generating a material request plan for producing the item using the customer order and the current state of the available inventory;
means for executing the material request plan, the means for executing the material request plan including means for netting deliveries of material with planned requests for material during the executing of the material request plan. - View Dependent Claims (15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26)
-
-
27. An apparatus for scheduling work and delivery of material for items in a factory comprising:
-
an obtaining module, the obtaining module obtaining a customer order, the customer order including an item ordered by a customer, the item having an associated quantity of a material to produce;
a determining module, the determining module determining a current state of an available inventory of material from a plurality of material sources;
a generating module, the generating module generating a material request plan for producing the item using the customer order and the current state of the available inventory;
a plan execution module, the plan execution module executing the material request plan, the plan execution module including a netting module, the netting module netting deliveries of material with planned requests for material during the executing of the material request plan. - View Dependent Claims (28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39)
-
Specification