Economic analysis and planning model for deconstruction of large scale industrial facilities

  • US 20040181422A1
  • Filed: 03/04/2004
  • Published: 09/16/2004
  • Est. Priority Date: 09/07/2001
  • Status: Abandoned Application
First Claim
Patent Images

1. A computer-implemented method of planning, monitoring, and implementing a deconstruction procedure on a facility, comprising the steps of:

  • gathering facility data concerning the facility and storing said data in a project database;

    comparing the facility data with historical data from a historical database and storing the results of said comparison in said project database;

    preparing an initial deconstruction plan based on said comparison and storing said initial deconstruction plan in said project database;

    conducting a scrap/recycle analysis on the facility based upon said facility data and said historical data, developing a scrap/recycle plan based on a result of said scrap/recycle analysis, and storing said result and said scrap/recycle plan in said project database;

    updating said initial deconstruction plan to incorporate said result and said scrap/recycle plan;

    identifying and assessing potential deconstruction sites in view of said updated deconstruction plan and selecting a preferred site to perform the deconstruction;

    performing said deconstruction at said selected preferred site and updating said project database as said deconstruction is performed;

    executing said scrap/recycling plan; and

    updating said project database and said historical database with data pertaining to said performed deconstruction and executed scrap/recycling plan.