Cogeneration system, operation controller for cogeneration facility, and operation program for cogeneration facility
First Claim
1. A cogeneration system, comprising:
- a cogeneration facility for generating power and heat;
a plurality of consuming apparatuses consuming the power and/or heat generated by the cogeneration facility; and
an operation controller for controlling the operation of the cogeneration facility;
wherein the consuming apparatuses include a first consuming apparatus capable of automatically transmitting operation schedule information of its own to the operation controller, and a second consuming apparatus incapable of automatically transmitting the operation schedule information of its own;
the operation controller compares an operation starting time (t1) of the consuming apparatuses based on the operation schedule information collected from the first consuming apparatus and a consumption starting time (t2) based on the prediction of a total power and/or heat consumption of the first and second consuming apparatuses; and
the operation starting time of the cogeneration facility is determined with priority given to the operation starting time (t1) if the operation starting time (t1) is earlier than the consumption starting time (t2) while being determined with priority given to the consumption starting time (t2) if the operation starting time (t1) is later than the consumption starting time (t2).
1 Assignment
0 Petitions
Accused Products
Abstract
An operating condition determiner compares an operation starting time (t1) of network-connected first consuming apparatuses received by a schedule information receiver and a consumption starting time (t2) predicted by a predicting system based on a total consumption amount of the first consuming apparatuses and a second consuming apparatus, which is not network-connected, and determines the operation starting time (t1) as an operation starting time of a fuel cell if the operation starting time (t1) is earlier than the consumption starting time (t2) while determining the consumption starting time (t2) as such if the operation starting time (t1) is later than the consumption starting time (t2), so that the fuel cell can stably generate power. The fuel cell can stably supply power at a time when the consuming apparatuses start consuming power. The merit of introducing a cogeneration facility can be sufficiently exhibited even if both consuming apparatuses provided with a network connecting function and those provided with no such function exist.
-
Citations
36 Claims
-
1. A cogeneration system, comprising:
-
a cogeneration facility for generating power and heat;
a plurality of consuming apparatuses consuming the power and/or heat generated by the cogeneration facility; and
an operation controller for controlling the operation of the cogeneration facility;
wherein the consuming apparatuses include a first consuming apparatus capable of automatically transmitting operation schedule information of its own to the operation controller, and a second consuming apparatus incapable of automatically transmitting the operation schedule information of its own;
the operation controller compares an operation starting time (t1) of the consuming apparatuses based on the operation schedule information collected from the first consuming apparatus and a consumption starting time (t2) based on the prediction of a total power and/or heat consumption of the first and second consuming apparatuses; and
the operation starting time of the cogeneration facility is determined with priority given to the operation starting time (t1) if the operation starting time (t1) is earlier than the consumption starting time (t2) while being determined with priority given to the consumption starting time (t2) if the operation starting time (t1) is later than the consumption starting time (t2).
-
-
2. A cogeneration system, comprising:
-
a cogeneration facility for generating power and heat;
a plurality of consuming apparatuses consuming the power and/or heat generated by the cogeneration facility; and
an operation controller for controlling the operation of the cogeneration facility;
wherein the consuming apparatuses include a first consuming apparatus capable of automatically transmitting operation schedule information of its own to the operation controller, and a second consuming apparatus incapable of automatically transmitting the operation schedule information of its own;
the operation controller compares a first operation starting time (t3) of the cogeneration facility which is at or later than an operation starting time (t1) of the consuming apparatuses based on the operation schedule information collected from the first consuming apparatus and should be substantially determined based only on the operation schedule information collected from the first consuming apparatus and a second operation starting time (t4) of the cogeneration facility which should be substantially determined based on the prediction of a total power and/or heat consumption of the first and second consuming apparatuses; and
the operation starting time of the cogeneration facility is determined with priority given to the first operation starting time (t3) if the first operation starting time (t3) is earlier than the second operation starting time (t4) while being determined with priority given to the second operation starting time (t4) if the first operation starting time (t3) is later than the second operation starting time (t4). - View Dependent Claims (3, 4, 5, 6)
-
-
7. A cogeneration system, comprising:
-
a cogeneration facility for generating power and heat, a plurality of consuming apparatuses consuming the power and/or heat generated by the cogeneration facility, and an operation controller for controlling the operation of the cogeneration facility, wherein the consuming apparatuses include a first consuming apparatus capable of automatically transmitting operation schedule information of its own to the operation controller, and a second consuming apparatus incapable of automatically transmitting the operation schedule information of its own, a specified value X of a power and/or heat consumption amount for starting the operation of the cogeneration facility is set based on a power and/or heat generation amount variable range of the cogeneration facility, the operation controller includes;
a consumption amount calculator for calculating a total power and/or heat consumption amount predicted value (A11) of the first and second consuming apparatuses predicted based on a measurement value of a total power and/or heat consumption amount of the first and second consuming apparatuses, and a power and/or heat consumption amount predicted value (A12) of the first consuming apparatus predicted based on a measurement value of a power and/or heat consumption amount of the first consuming apparatus, and calculating a power and/or heat consumption amount predicted value (A13) of only the second consuming apparatus by subtracting the consumption amount predicted value (A12) from the consumption amount predicted value (A11), a consumption amount predictor for obtaining a power and/or heat consumption amount predicted value (A14) of the first consuming apparatus predicted based on the operation schedule information actually set in the first consuming apparatus, and a total consumption amount predictor for obtaining a total power and/or heat consumption amount predicted value (A15) by adding the consumption amount predicted values (A13) and (A14), and a time at which the consumption amount predicted value (A15) becomes equal to or above the specified value X is determined as an operation starting time (t5) of the cogeneration facility. - View Dependent Claims (8, 9)
-
-
10. A cogeneration system, comprising:
-
a cogeneration facility for generating power and heat, a plurality of consuming apparatuses consuming the power and/or heat generated by the cogeneration facility, and an operation controller for controlling the operation of the cogeneration facility, wherein the consuming apparatuses include a first consuming apparatus capable of automatically transmitting operation schedule information of its own to the operation controller, and a second consuming apparatus incapable of automatically transmitting the operation schedule information of its own, a specified value X of a power and/or heat consumption amount for starting the operation of the cogeneration facility is set based on a power and/or heat generation amount variable range of the cogeneration facility, the operation controller includes;
a consumption amount calculator for calculating a power and/or heat consumption amount (A21-A22) of only the second consuming apparatus by subtracting a measurement value (A22) of a power and/or heat consumption amount of the first consuming apparatus from a measurement value (A21) of a total power and/or heat consumption amount of the first and second consuming apparatuses, and calculating a consumption amount predicted value (A23) of only the second consuming apparatuses based on the calculated consumption amount (A21-A22), a consumption amount predictor for obtaining a power and/or heat consumption amount predicted value (A24) of the first consuming apparatus predicted based on the operation schedule information actually set in the first consuming apparatus, and a total consumption amount predictor for obtaining a total power and/or heat consumption amount predicted value (A25) by adding the consumption amount predicted values (A23) and (A24), and a time at which the consumption amount predicted value (A25) becomes equal to or above the specified value X is determined as an operation starting time (t5) of the cogeneration facility. - View Dependent Claims (11, 12)
-
-
13. An operation controller for controlling the operation of a cogeneration facility for supplying power and heat to a plurality of consuming apparatuses consuming power and/or heat, the operation controller being used in the case that the consuming apparatuses include a first consuming apparatus capable of automatically transmitting operation schedule information of its own to the operation controller, and a second consuming apparatus incapable of automatically transmitting the operation schedule information of its own, wherein:
-
an operation starting time (t1) of the consuming apparatuses based on the operation schedule information collected from the first consuming apparatus and a consumption starting time (t2) based on the prediction of a total power and/or heat consumption of the first and second consuming apparatuses are compared, and the operation starting time of the cogeneration facility is determined with priority given to the operation starting time (t1) if the operation starting time (t1) is earlier than the consumption starting time (t2) while being determined with priority given to the consumption starting time (t2) if the operation starting time (t1) is later than the consumption starting time (t2).
-
-
14. An operation controller for controlling the operation of a cogeneration facility for supplying power and heat to a plurality of consuming apparatuses consuming power and/or heat, the operation controller being used in the case that the consuming apparatuses include a first consuming apparatus capable of automatically transmitting operation schedule information of its own to the operation controller, and a second consuming apparatus incapable of automatically transmitting the operation schedule information of its own, wherein:
-
a first operation starting time (t3) of the cogeneration facility which is at or later than an operation starting time (t1) of the consuming apparatuses based on the operation schedule information collected from the first consuming apparatus and should be substantially determined based only on the operation schedule information collected from the first consuming apparatus and a second operation starting time (t4) of the cogeneration facility which should be substantially determined based on the prediction of a total power and/or heat consumption of the first and second consuming apparatuses are compared, and the operation starting time of the cogeneration facility is determined with priority given to the first operation starting time (t3) if the first operation starting time (t3) is earlier than the second operation starting time (t4) while being determined with priority given to the second operation starting time (t4) if the first operation starting time (t3) is later than the second operation starting time (t4). - View Dependent Claims (15, 16, 17, 18)
-
-
19. An operation controller for controlling the operation of a cogeneration facility for supplying power and heat to a plurality of consuming apparatuses consuming power and/or heat, the operation controller being used in the case that the consuming apparatuses include a first consuming apparatus capable of automatically transmitting operation schedule information of its own to the operation controller, and a second consuming apparatus incapable of automatically transmitting the operation schedule information of its own, wherein:
-
a specified value X of a power and/or heat consumption amount for starting the operation of the cogeneration facility is set based on a power and/or heat generation amount variable range of the cogeneration facility, the operation controller comprises;
a consumption amount calculator for calculating a total power and/or heat consumption amount predicted value (A11) of the first and second consuming apparatuses predicted based on a measurement value of a total power and/or heat consumption amount of the first and second consuming apparatuses, and a power and/or heat consumption amount predicted value (A12) of the first consuming apparatus predicted based on a measurement value of a power and/or heat consumption amount of the first consuming apparatus, and calculating a power and/or heat consumption amount predicted value (A13) of only the second consuming apparatus by subtracting the consumption amount predicted value (A12) from the consumption amount predicted value (A11), a consumption amount predictor for obtaining a power and/or heat consumption amount predicted value (A14) of the first consuming apparatus predicted based on the operation schedule information actually set in the first consuming apparatus, and a total consumption amount predictor for obtaining a total power and/or heat consumption amount predicted value (A15) by adding the consumption amount predicted values (A13) and (A14), and a time at which the consumption amount predicted value (A15) becomes equal to or above the specified value X is determined as an operation starting time (t5) of the cogeneration facility. - View Dependent Claims (20, 21)
-
-
22. An operation controller for controlling the operation of a cogeneration facility for supplying power and heat to a plurality of consuming apparatuses consuming power and/or heat, the operation controller being used in the case that the consuming apparatuses include a first consuming apparatus capable of automatically transmitting operation schedule information of its own to the operation controller, and a second consuming apparatus incapable of automatically transmitting the operation schedule information of its own, wherein:
-
a specified value X of a power and/or heat consumption amount for starting the operation of the cogeneration facility is set based on a power and/or heat generation amount variable range of the cogeneration facility, the operation controller comprises;
a consumption amount calculator for calculating a power and/or heat consumption amount (A21-A22) of only the second consuming apparatus by subtracting a measurement value (A22) of a power and/or heat consumption amount of the first consuming apparatus from a measurement value (A21) of a total power and/or heat consumption amount of the first and second consuming apparatuses, and calculating a consumption amount predicted value (A23) of only the second consuming apparatuses based on the calculated consumption amount (A21-A22), a consumption amount predictor for obtaining a power and/or heat consumption amount predicted value (A24) of the first consuming apparatus predicted based on the operation schedule information actually set in the first consuming apparatus, and a total consumption amount predictor for obtaining a total power and/or heat consumption amount predicted value (A25) by adding the consumption amount predicted values (A23) and (A24), and a time at which the consumption amount predicted value (A25) becomes equal to or above the specified value X is determined as an operation starting time (t5) of the cogeneration facility. - View Dependent Claims (23, 24)
-
-
25. An operation control program for controlling the operation of a cogeneration facility for supplying power and heat to a plurality of consuming apparatuses consuming power and/or heat, the operation controller being used in the case that the consuming apparatuses include a first consuming apparatus capable of automatically transmitting operation schedule information of its own to the operation controller, and a second consuming apparatus incapable of automatically transmitting the operation schedule information of its own, the operation control program causing the implementation of operation steps of:
-
obtaining and comparing an operation starting time (t1) of the consuming apparatuses based on the operation schedule information collected from the first consuming apparatus and a consumption starting time (t2) based on the prediction of a total power and/or heat consumption of the first and second consuming apparatuses, and determining the operation starting time of the cogeneration facility with priority given to the operation starting time (t1) if the operation starting time (t1) is earlier than the consumption starting time (t2) while determining it with priority given to the consumption starting time (t2) if the operation starting time (t1) is later than the consumption starting time (t2).
-
-
26. An operation control program for controlling the operation of a cogeneration facility for supplying power and heat to a plurality of consuming apparatuses consuming power and/or heat, the operation controller being used in the case that the consuming apparatuses include a first consuming apparatus capable of automatically transmitting operation schedule information of its own to the operation controller, and a second consuming apparatus incapable of automatically transmitting the operation schedule information of its own, the operation control program causing the implementation of operation steps of:
-
obtaining and comparing a first operation starting time (t3) of the cogeneration facility which is at or later than an operation starting time (t1) of the consuming apparatuses based on the operation schedule information collected from the first consuming apparatus and should be substantially determined based only on the operation schedule information collected from the first consuming apparatus and a second operation starting time (t4) of the cogeneration facility which should be substantially determined based on the prediction of a total power and/or heat consumption of the first and second consuming apparatuses, and determining the operation starting time of the cogeneration facility with priority given to the first operation starting time (t3) if the first operation starting time (t3) is earlier than the second operation starting time (t4) while determining it with priority given to the second operation starting time (t4) if the first operation starting time (t3) is later than the second operation starting time (t4). - View Dependent Claims (27, 28, 29, 30)
-
-
31. An operation control program for controlling the operation of a cogeneration facility for supplying power and heat to a plurality of consuming apparatuses consuming power and/or heat, the operation controller being used in the case that the consuming apparatuses include a first consuming apparatus capable of automatically transmitting operation schedule information of its own to the operation controller, and a second consuming apparatus incapable of automatically transmitting the operation schedule information of its own, the operation control program causing the implementation of operation steps of:
-
receiving a specified value X of a power and/or heat consumption amount for starting the operation of the cogeneration facility as a set value based on a power and/or heat generation amount variable range of the cogeneration facility obtaining a total power and/or heat consumption amount predicted value (A11) of the first and second consuming apparatuses predicted based on a measurement value of a total power and/or heat consumption amount of the first and second consuming apparatuses, and a power and/or heat consumption amount predicted value (A12) of the first consuming apparatus predicted based on a measurement value of a power and/or heat consumption amount of the first consuming apparatus, and calculating a power and/or heat consumption amount predicted value (A13) of only the second consuming apparatus by subtracting the consumption amount predicted value (A12) from the consumption amount predicted value (A11), obtaining a power and/or heat consumption amount predicted value (A14) of the first consuming apparatus predicted based on the operation schedule information actually set in the first consuming apparatus, and obtaining a total power and/or heat consumption amount predicted value (A15) by adding the consumption amount predicted values (A13) and (A14), and determining a time at which the consumption amount predicted value (A15) becomes equal to or above the specified value X as an operation starting time (t5) of the cogeneration facility. - View Dependent Claims (32, 33)
-
-
34. An operation control program for controlling the operation of a cogeneration facility for supplying power and heat to a plurality of consuming apparatuses consuming power and/or heat, the operation controller being used in the case that the consuming apparatuses include a first consuming apparatus capable of automatically transmitting operation schedule information of its own to the operation controller, and a second consuming apparatus incapable of automatically transmitting the operation schedule information of its own, the operation control program causing the implementation of operation steps of:
-
receiving a specified value X of a power and/or heat consumption amount for starting the operation of the cogeneration facility as a set value based on a power and/or heat generation amount variable range of the cogeneration facility, calculating a power and/or heat consumption amount (A21-A22) of only the second consuming apparatus by subtracting a measurement value (A22) of a power and/or heat consumption amount of the first consuming apparatus from a measurement value (A21) of a total power and/or heat consumption amount of the first and second consuming apparatuses, and calculating a consumption amount predicted value (A23) of only the second consuming apparatuses based on the calculated consumption amount (A21-A22), obtaining a power and/or heat consumption amount predicted value (A24) of the first consuming apparatus predicted based on the operation schedule information actually set in the first consuming apparatus, and obtaining a total power and/or heat consumption amount predicted value (A25) by adding the consumption amount predicted values (A23) and (A24), and determining a time at which the consumption amount predicted value (A25) becomes equal to or above the specified value X as an operation starting time (t5) of the cogeneration facility. - View Dependent Claims (35, 36)
-
Specification