System, method and article of manufacture for alerting a manager of a critical outstanding task
First Claim
Patent Images
1. A computer-readable medium encoded with a computer program for directing a computer to implement a critical path scheduling system for a construction project, the program comprising:
- a project task manager program segment for directing the computer to receive a plurality of construction project task records including task documents, to identify critical project tasks, to generate a critical path schedule based on the critical project tasks, to allow a user to update the project task records, to adjust the critical path schedule in response to an updated record, and to present the critical path schedule to the user; and
a bid manager program segment for directing the computer to receive bids relating to the plurality of project tasks, to include each bid in a related task record, to generate a budget estimate based on the bids, to adjust the budget estimate in response to an updated task record, and to present the budget estimate to the user.
0 Assignments
0 Petitions
Accused Products
Abstract
A system, method and computer program product are provided for alerting a manager of an outstanding task. Initially, a database of tasks is maintained. Further, a due date associated with the tasks is determined. During use, a status of the tasks is monitored. As such, alerts may be generated based on the due date and status of the tasks.
-
Citations
12 Claims
-
1. A computer-readable medium encoded with a computer program for directing a computer to implement a critical path scheduling system for a construction project, the program comprising:
-
a project task manager program segment for directing the computer to receive a plurality of construction project task records including task documents, to identify critical project tasks, to generate a critical path schedule based on the critical project tasks, to allow a user to update the project task records, to adjust the critical path schedule in response to an updated record, and to present the critical path schedule to the user; and
a bid manager program segment for directing the computer to receive bids relating to the plurality of project tasks, to include each bid in a related task record, to generate a budget estimate based on the bids, to adjust the budget estimate in response to an updated task record, and to present the budget estimate to the user. - View Dependent Claims (2, 3, 4, 5, 6)
-
-
7. A computer-readable medium encoded with a computer program for directing a computer to implement a critical path scheduling system for a construction project, the program comprising:
-
a project task manager program segment for directing the computer to receive a plurality of construction project task records including task documents, to identify critical project tasks, to generate a critical path schedule based on the critical project tasks, to allow a user to update a project task record by generating a browser that permits the user to view and update documents, to adjust the critical path schedule in response to the updated record, and to present the critical path schedule to the user; and
a bid manager program segment for directing the computer to receive bids relating to the plurality of project tasks, to include each bid in a related task record, to generate a budget estimate based on the bids, to calculate a total bid amount for each of a plurality of bidders, to adjust the budget estimate in response to an updated task record, and to present the budget estimate and the total bid amount for each bidder to the user. - View Dependent Claims (8, 9, 10)
-
-
11. A computer-readable medium encoded with a computer program for directing a computer to implement a critical path scheduling system for a construction project, the program comprising:
-
a project task manager program segment for directing the computer to receive a plurality of construction project task records including task documents, to identify critical project tasks using the records, to generate a critical path schedule based on the critical project tasks, to generate a browser that permits the user to view and update the documents only after the user has completed a secure login, to adjust the critical path schedule in response to an updated record, and to present the critical path schedule to the user; and
a bid manager program segment for directing the computer to receive bids relating to the plurality of project tasks, to include each bid in a related task record, to generate a budget estimate based on the bids, to calculate a total bid amount for each of a plurality of bidders, to calculate a total bid amount for each of a plurality of projects, to adjust the budget estimate in response to an updated task record, and to present the budget estimate to the user. - View Dependent Claims (12)
-
Specification