Facilitation of multi-project management using task hierarchy
First Claim
1. A method on a computer for providing critical chain-based project management, comprising:
- receiving at least one project plan for a project comprising a plurality of tasks;
calculating a task priority for each of the plurality of tasks, based on the at least one project plan;
receiving at least one sub-task for a first task of the plurality of tasks; and
assigning the at least one sub-task a task priority identical to the task priority of the first task.
1 Assignment
0 Petitions
Accused Products
Abstract
A method on a computer for providing critical chain-based project management is disclosed. The method includes receiving at least one project plan for a project comprising a plurality of tasks and calculating a task priority for each of the plurality of tasks based on the at least one project plan. The method further includes receiving at least one sub-task for a first task of the plurality of tasks and assigning the at least one sub-task a task priority identical to the task priority of the first task. In one alternative, the method further includes receiving a new task priority for the first task, assigning the new task priority to the first task and assigning the new task priority to the at least one sub-task of the first task. The method may also include an interface to allow starting of sub-tasks only when the parent task is started.
49 Citations
17 Claims
-
1. A method on a computer for providing critical chain-based project management, comprising:
-
receiving at least one project plan for a project comprising a plurality of tasks;
calculating a task priority for each of the plurality of tasks, based on the at least one project plan;
receiving at least one sub-task for a first task of the plurality of tasks; and
assigning the at least one sub-task a task priority identical to the task priority of the first task. - View Dependent Claims (2, 3, 4, 5, 6)
-
-
7. A computer system for providing critical chain-based project management, comprising:
-
an interface for receiving at least one project plan for a project comprising a plurality of tasks wherein at least one sub-task corresponds to a first task of the plurality of tasks;
a processor configured for;
calculating a task priority for each of the plurality of tasks, based on the at least one project plan; and
assigning the at least one sub-task a task priority identical to the task priority of the first task. - View Dependent Claims (8, 9, 10, 11, 12)
-
-
13. A computer readable medium including computer instructions for providing project management, the computer instructions including instructions for:
-
receiving at least one project plan for a project comprising a plurality of tasks;
calculating a task priority for each of the plurality of tasks, based on the at least one project plan;
receiving at least one sub-task for a first task of the plurality of tasks; and
assigning the at least one sub-task a task priority identical to the task priority of the first task. - View Dependent Claims (14, 15, 16, 17)
-