Operation information control device for construction machine and construction machine operation information control system provided with it
First Claim
1. An operational information managing apparatus (60) for use in a construction machine (1) to manage operating situations of said construction machine, wherein said apparatus comprises:
- storage means (67) for taking in and storing plural kinds of operational information regarding said construction machine (1) as operational data; and
control means (65) for extracting top priority operational data from among the plural kinds of operational data stored in said storage means (67).
1 Assignment
0 Petitions
Accused Products
Abstract
A data recording unit 60 for managing operating situations of a hydraulic excavator 1 comprises a RAM 67 for taking in and storing plural kinds of operational information regarding the hydraulic excavator 1 as operational data, and a CPU 65 for extracting top priority operational data from among the plural kinds of operational data stored in the RAM 67, and transmitting the extracted data to the supervising side via satellite communication. Top priority data among the plural kinds of operational data of the hydraulic excavator, which may bring the hydraulic excavator into rest, can be presented to a supervisor of the hydraulic excavator, etc.
-
Citations
14 Claims
-
1. An operational information managing apparatus (60) for use in a construction machine (1) to manage operating situations of said construction machine, wherein said apparatus comprises:
-
storage means (67) for taking in and storing plural kinds of operational information regarding said construction machine (1) as operational data; and
control means (65) for extracting top priority operational data from among the plural kinds of operational data stored in said storage means (67). - View Dependent Claims (5, 6, 7, 8, 9, 10)
-
-
2. An operational information managing apparatus (60) for use in a construction machine (1) to manage operating situations of said construction machine, wherein said apparatus comprises:
-
storage means (67) for taking in and storing plural kinds of operational information regarding said construction machine (1) as operational data; and
control means (65) for extracting top priority operational data from among the plural kinds of operational data stored in said storage means (67), and outputting the extracted data to the supervising side. - View Dependent Claims (14)
-
-
3. An operational information managing apparatus (60) for use in a construction machine (1) to manage operating situations of said construction machine, wherein said apparatus comprises:
-
storage means (67) for taking in and storing plural kinds of operational information regarding said construction machine (1) as operational data; and
control means (65) for extracting preset top priority operational data from among the plural kinds of operational data stored in said storage means (67), and outputting the extracted data to the supervising side.
-
-
4. An operational information managing apparatus (60) for use in a construction machine (1) to manage operating situations of said construction machine, wherein said apparatus comprises:
-
storage means (67) for taking in and storing plural kinds of operational information regarding said construction machine (1) as operational data; and
control means (65) for extracting selectively-set top priority operational data from among the plural kinds of operational data stored in said storage means (67), and outputting the extracted data to the supervising side.
-
-
11. An operational information managing system (2) for a construction machine, said system comprising:
-
a first communication network (2A) including an engine monitor unit (51R, 51L) for detecting operational data regarding the operating status of an engine (32);
a second communication network (2B) including a machine body control unit (52) for detecting operational data regarding a body of a construction machine (1) and an electric lever control unit (53) for detecting operational data regarding the operating status of an electric lever of said construction machine (1); and
an operational information managing apparatus (60) connected to said first communication network and said second communication network, taking in a third kind of operational data from said first communication network and a fourth kind of operational data from said second communication network, and computing and outputting top priority operational data based on the third kind of operational data and the fourth kind of operational data. - View Dependent Claims (12, 13)
-
Specification