Schedule creation method, schedule creation system, unexperienced schedule prediction method, and learning schedule evaluation display method
First Claim
1. A schedule creating method, wherein a schedule condition for an occurrence of an event relating a content, is constituted by a timing condition including:
- a presentation unit configured to be a minimum term for the occurrence of the event relating the content;
an interval configured to be longer than the presentation unit for the occurrence of the event and be a term from a beginning of the event to an occurrence of a next event;
an event cycle unit configured to be a predetermined term shorter than the interval and distribute occurrences of the event;
a condition unit configured to be longer than the presentation unit, be a term shorter than the event cycle unit, and arrange the presentation unit of the event uniformly; and
a delay term configured to express a difference of starting points of schedules when a plurality of schedules are stared.
0 Assignments
0 Petitions
Accused Products
Abstract
A schedule creating method capable of performing an analysis and a prediction with taking an individual attribute or quality of content into consideration by collecting an individual reaction according to a predetermined schedule, a method for predicting an individual reaction to an inexperienced schedule utilizing the above schedule, and a learning schedule assessment displaying method for displaying the results of the prediction are provided. A timing unit includes a presentation unit being a minimum term of generating the event relating the content, an event cycle unit being a predetermined term shorter than an interval being longer than the presentation unit of generating the event and being from a beginning of the event and till an occurrence of a next event, a condition unit being longer than the presentation unit and shorter than the event cycle unit, and a delay term for expressing a difference of starting points when a plurality of schedules are stared. By using the timing unit, a schedule in which an event relating to a specific content occurs.
54 Citations
14 Claims
-
1. A schedule creating method, wherein
a schedule condition for an occurrence of an event relating a content, is constituted by a timing condition including: -
a presentation unit configured to be a minimum term for the occurrence of the event relating the content;
an interval configured to be longer than the presentation unit for the occurrence of the event and be a term from a beginning of the event to an occurrence of a next event;
an event cycle unit configured to be a predetermined term shorter than the interval and distribute occurrences of the event;
a condition unit configured to be longer than the presentation unit, be a term shorter than the event cycle unit, and arrange the presentation unit of the event uniformly; and
a delay term configured to express a difference of starting points of schedules when a plurality of schedules are stared. - View Dependent Claims (2, 3, 4)
-
-
5. A schedule generating system, comprising:
-
an input means for inputting a predetermined information and characterized in that based on the input information, a maximum number of condition unit considerable in an event cycle unit and a maximum number of the event cycle unit including all schedule terms are generated, in order to constitute a schedule condition for an occurrence of an event relating a content by a timing condition, the timing condition including;
a presentation unit configured to be a minimum term for the occurrence of the event relating the content;
an interval configured to be longer than the presentation unit of generating the event and be a term from a beginning of the event to an occurrence of a next event;
an event cycle unit configured to be a predetermined term shorter than the interval and distribute occurrences of the event;
a condition unit configured to be longer than the presentation unit, be a term shorter than the event cycle unit, and arrange the presentation unit of the event uniformly; and
a delay term configured to express a difference of starting points of schedules when a plurality of schedules are stared. - View Dependent Claims (6)
-
-
7. An inexperienced schedule predicting method, comprising:
-
providing a predetermined term equal to or longer than the presentation unit which is a shortest period for generating the event and shorter than the interval from a beginning of the event till an occurrence of a next event as an event cycle unit;
using a schedule arranging a content so that a particular event relating each content is generated once in the event cycle unit;
collecting reactions of experience to the content in time series; and
predicting a future reaction pattern based on the collected reactions, in order to generate a schedule, of a set of one or more contents, in which events relating to all contents repeatedly occur at a predetermined timing. - View Dependent Claims (8, 9, 10)
-
-
11. An inexperienced schedule predicting method, comprising:
-
providing a predetermined term being longer than the presentation unit of generating the event and being from a beginning of the event to an occurrence of a next event as an event cycle unit;
generating a schedule so that an event is generated once in the event cycle unit;
cording an event occurrence an individual reaction to the event respectively in a plurality of relating events and collecting in time series;
comparing reaction process pattern of another person extracted based on the final reaction result with an individual reaction process pattern; and
providing a schedule of the other having a similar reaction process pattern as a future schedule of the individual, in order to use the schedule, of a set of one or more contents, in which a specific event repeatedly occur at a predetermined timing. - View Dependent Claims (12)
-
-
13. A learning schedule assessment displaying method for a learner'"'"'s assessment displaying system in which a learner'"'"'s terminal and a server for displaying a learning achievement in a website are connected via a network, the method comprising:
-
providing a predetermined term equal to or longer than the presentation unit which is a shortest period for generating the event and shorter than the interval from a beginning of the event till an occurrence of a next event as an event cycle unit;
using a learning schedule arranging a content so that a particular event relating each content is generated once in the event cycle unit;
assessing the learning achievement relating the content in time series; and
displaying data relating the learning achievement, a learning content and a link of relating site corresponding to the learning achievement on the learner'"'"'s terminal when the assessment of the learning achievement reaches a predetermined level, in order to generate a schedule, of a set of one or more contents, in which events relating to all contents repeatedly occur at a predetermined timing.
-
-
14. A learning schedule assessment displaying method of a learner'"'"'s assessment displaying system in which a learner'"'"'s terminal and a server for displaying a learning achievement a website are connected via a network, the method comprising:
-
means for registering a searching word used by a learner, with a classification according to learning ability levels of the learners;
means for registering a site to which the learner visited in correspondence with the site to the registered searching word; and
means for counting up a number of times for visiting a site when search is performed with a searching word same as the registered searching word and a cite same as the registered site is visited, wherein a search result is displayed in an order of larger number of visiting times on the learner'"'"'s terminal.
-
Specification