Method of synchronizing with an uplink channel and a method of determining a propagation delay in a wireless communications system
First Claim
1. A method of synchronizing a target base station with a mobile station in a wireless communications system, comprising:
- calculating a propagation delay between the target base station and the mobile station; and
sending the calculated propagation delay to the target base station.
5 Assignments
0 Petitions
Accused Products
Abstract
A method of synchronizing with an uplink channel and a method of determining a propagation delay in a wireless communications system are provided. In the example method of synchronizing, a propagation delay between a target base station and a mobile station is calculated. Then, the calculated propagation delay is sent to the target base station. In the example method of determining a propagation delay, a first signal is received indicating a first measured chip offset between a downlink channel of a serving base station and a pilot signal of the target base station. A second signal indicating a second measured chip offset between an uplink channel of the mobile station and a pilot signal of the target base station is then received. A propagation delay between the target base station and the mobile station is calculated based at least in part on the first and second measured chip offsets.
57 Citations
21 Claims
-
1. A method of synchronizing a target base station with a mobile station in a wireless communications system, comprising:
-
calculating a propagation delay between the target base station and the mobile station; and
sending the calculated propagation delay to the target base station. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10)
-
-
11. A method of synchronizing a target base station with a mobile station in a wireless communications system, comprising:
-
receiving a signal indicating a propagation delay between the target base station and the mobile station; and
synchronizing with an uplink channel received from the mobile station based on the indicated propagation delay. - View Dependent Claims (12, 13, 14, 15, 16)
-
-
17. A method of calculating a propagation delay between a target base station and a mobile station in a wireless communications system, comprising:
-
first receiving a first signal indicating a first measured chip offset between a downlink channel of a serving base station and a pilot signal of the target base station;
second receiving a second signal indicating a second measured chip offset between an uplink channel of a the mobile station and a pilot signal of the target base station; and
calculating the propagation delay between the target base station and the mobile station based at least in part on the first and second measured chip offsets. - View Dependent Claims (18, 19, 20, 21)
-