OVERHEAD POWER TRANSMISSION LINE CONDUCTOR SELECTION
First Claim
1. A computer-implemented method of evaluating an electric conductor for an overhead power transmission line, comprising:
- receiving requirements data defining requirements for an overhead power transmission line comprising at least a span value, a maximum sag value, and a maximum tension value;
receiving conductor data that define at least two conductors to be evaluated;
after receiving conductor data for the plurality of conductors to be evaluated, automatically modeling expected operating performance for at least two conductors using conductor assessment software running on a computer, wherein modeling at least comprises, for at least one of the conductors to be evaluated, calculating the conductor'"'"'s maximum ampacity within the constraints defined by the requirements data; and
,based on the modeling, identifying at least one conductor that meets the requirements for the power transmission line using the conductor assessment software.
1 Assignment
0 Petitions
Accused Products
Abstract
In general the invention is directed to systems and methods to identify conductors that may be used as part of a power transmission line system. In one embodiment, the invention is directed to a computer-implemented method of evaluating an electric conductor for an overhead power transmission line, comprising: receiving requirements data defining requirements for an overhead power transmission line; receiving conductor data that define at least two conductors to be evaluated; after receiving conductor data for the plurality of conductors to be evaluated, automatically modeling expected operating performance for at least two conductors using conductor assessment software running on a computer, wherein modeling at least comprises, for at least one of the conductors to be evaluated, calculating the conductor'"'"'s maximum ampacity within the constraints defined by the requirements data; and, based on the modeling, identifying at least one conductor that meets the requirements for the power transmission line.
16 Citations
30 Claims
-
1. A computer-implemented method of evaluating an electric conductor for an overhead power transmission line, comprising:
-
receiving requirements data defining requirements for an overhead power transmission line comprising at least a span value, a maximum sag value, and a maximum tension value; receiving conductor data that define at least two conductors to be evaluated; after receiving conductor data for the plurality of conductors to be evaluated, automatically modeling expected operating performance for at least two conductors using conductor assessment software running on a computer, wherein modeling at least comprises, for at least one of the conductors to be evaluated, calculating the conductor'"'"'s maximum ampacity within the constraints defined by the requirements data; and
,based on the modeling, identifying at least one conductor that meets the requirements for the power transmission line using the conductor assessment software. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13)
-
-
14. A computer-implemented method of evaluating an electric conductor for an overhead power transmission line, comprising:
-
receiving requirements data defining requirements for an overhead power transmission line comprising at least a span value, minimum ampacity, and a maximum tension value; receiving conductor data that define at least two conductors to be evaluated; after receiving conductor data for the plurality of conductors to be evaluated, automatically modeling expected operating performance for at least two conductors using conductor assessment software running on a computer, wherein modeling at least comprises, for at least one of the conductors to be evaluated, calculating the conductor'"'"'s minimum sag within the constraints defined by the requirements data; and
,based on the modeling, identifying at least one conductor that meets the requirements for the power transmission line using the conductor assessment software. - View Dependent Claims (15, 16, 17, 18, 19, 20, 21, 22, 23)
-
-
24. A computer-implemented method of evaluating an electric conductor for an overhead power transmission line, comprising:
-
receiving power transmission line data that defines an existing power transmission line; receiving a set of requirements data defining requirements for a replacement conductor from a user, at least one limitation of which is proposed by the conductor assessment software, and based on a limitation of the existing power transmission line; receiving conductor data that define at least two conductors to be evaluated; after receiving conductor data for the plurality of conductors to be evaluated, automatically modeling expected operating performance for at least two conductors using conductor assessment software running on a computer; and
,based on the modeling, identifying at least one conductor that meets the requirements for the power transmission line using the conductor assessment software. - View Dependent Claims (25, 26)
-
-
27. A computer-implemented method of evaluating an electric conductor for an overhead power transmission line, comprising:
-
receiving requirements data that define at least two requirements for an overhead power transmission line; receiving conductor data that define at least two conductors to be evaluated; receiving preference data that defines at least one design goal, wherein the design goal defines both “
a” and
“
b”
as follows;(a) a design goal variable, which is any variable that is among the requirements data, among the conductor data, among both the requirements data and the conductor data, or is the result of a calculation that involves data that is either among the requirements data or the conductor data, (b) for the design goal variable, preference data defining whether the variable should be maximized or minimized; after receiving requirements data, conductor data, and preference data, for the plurality of conductors to be evaluated, automatically modeling expected operating performance for at least two conductors using conductor assessment software running on a computer; and
,based on the modeling, identifying at least one conductor that meets the requirements for the power transmission line, and either maximizes or minimizes the design goal variable as defined by the preference data using the conductor assessment software. - View Dependent Claims (28)
-
-
29. A system for identifying conductors that meet requirements for an overhead power transmission line, comprising:
-
a database component operative to maintain a database identifying at least two conductors; a user interface component operative to receive information defining requirements for an overhead power transmission line, the requirements at least comprising a span value, a maximum sag value, and a maximum tension value; a modeling component operative to computationally evaluate the performance of at least two of the conductors maintained in the database component, wherein computational evaluation comprises calculating a conductor'"'"'s maximum ampacity with the constraints defined by the requirements data; and a reporting component operative to determine and present, based on the modeling component'"'"'s evaluation, conductors that meet requirements for the overhead power transmission line.
-
-
30. A method of selling a conductor an overhead power transmission line comprising:
-
receiving requirements for an overhead power transmission line; identifying a set of conductors that could meet the requirements of a power transmission line, at least one of the conductors from a manufacturer distinct from a manufacturer of another of the conductors; using a computer-implemented method to automatically model performance of at least two of the conductors against requirements of the power transmission line; generating a list of conductors that meet the requirements; and selling a conductor from the list of conductors that meet the requirements.
-
Specification