METHOD FOR PROJECT MANAGEMENT

  • US 20070288283A1
  • Filed: 06/07/2007
  • Published: 12/13/2007
  • Est. Priority Date: 06/09/2006
  • Status: Abandoned Application
First Claim
Patent Images

1. A method for project management by adding risk-based adjustments to a schedule for a project, the project having a plurality of tasks, each task having an estimated duration and one or more dependencies on other tasks, the project further having one of a plurality of team members assigned for executing each of the tasks and a project store for storing the task estimated duration, dependency and team member information for each task, the method comprising the steps of:

  • collecting all of the tasks in the project;

    collecting, for each task, all of the predecessor tasks from which the task has a dependency;

    adding to the collected predecessor tasks, for each predecessor task, any other predecessor tasks from which the predecessor task has dependencies until all predecessor tasks have been collected;

    adding a risk-based adjustment to the finish date of each of the collected predecessor tasks, the risk-based adjustment comprising;

    a distraction rate for the team member assigned to predecessor task; and

    a time estimation error rate for the team member assigned to the predecessor task; and

    rescheduling each of the tasks in the project to start on the business day after the latest finish date of any of the predecessor tasks of the task.

View all claims