Method and system for assessing schedule performance issues of a project
First Claim
1. A computer-implemented method of assessing schedule performance of a project, said method comprising one of:
- generating, by a computing application capable of managing said project, a Behind Schedule Performance Index (BSPI) that excludes an ahead of schedule component from a scheduled performance index (SPI) associated with said project, said ahead of schedule component being a first component of a schedule variance (SV) associated with said project;
generating, by said computing application, an ahead/behind trend graph having a first plurality of graphical indicators of ahead of schedule values associated with said project and a second plurality of graphical indicators of behind schedule values associated with said project, wherein said first plurality of graphical indicators and said second plurality of graphical indicators indicate that a portion of said project is behind schedule while said project, as a whole, is ahead of schedule;
generating, by said computing application, a behind schedule exception report that includes a first set of one or more tasks of said project that are behind schedule based on a baseline of said project and that excludes any task of said project that is ahead of schedule based on said baseline; and
generating, by said computing application, an ahead of schedule exception report that includes a second set of one or more tasks of said project that are ahead of schedule based on said baseline and that excludes any task of said project that is behind schedule based on said baseline.
1 Assignment
0 Petitions
Accused Products
Abstract
A computer-implemented method and system for assessing schedule performance issues of a project. A Behind Schedule Performance Index (BSPI), an ahead/behind trend graph, a behind schedule report or an ahead of schedule report is generated. The BSPI excludes an ahead of schedule component from the project'"'"'s scheduled performance index. The ahead/behind trend graph has ahead of schedule and behind schedule indicators indicating that a portion of the project is behind schedule while the project, as a whole, is ahead of schedule. The behind schedule report filters out ahead of schedule tasks and includes only behind schedule tasks. The ahead of schedule report filters out behind schedule tasks and includes only ahead of schedule tasks.
90 Citations
20 Claims
-
1. A computer-implemented method of assessing schedule performance of a project, said method comprising one of:
-
generating, by a computing application capable of managing said project, a Behind Schedule Performance Index (BSPI) that excludes an ahead of schedule component from a scheduled performance index (SPI) associated with said project, said ahead of schedule component being a first component of a schedule variance (SV) associated with said project; generating, by said computing application, an ahead/behind trend graph having a first plurality of graphical indicators of ahead of schedule values associated with said project and a second plurality of graphical indicators of behind schedule values associated with said project, wherein said first plurality of graphical indicators and said second plurality of graphical indicators indicate that a portion of said project is behind schedule while said project, as a whole, is ahead of schedule; generating, by said computing application, a behind schedule exception report that includes a first set of one or more tasks of said project that are behind schedule based on a baseline of said project and that excludes any task of said project that is ahead of schedule based on said baseline; and generating, by said computing application, an ahead of schedule exception report that includes a second set of one or more tasks of said project that are ahead of schedule based on said baseline and that excludes any task of said project that is behind schedule based on said baseline. - View Dependent Claims (2, 3, 4, 5, 6, 7)
-
-
8. A system for assessing schedule performance of a project in a computing environment, said method comprising one of:
-
means for generating, by a computing application capable of managing said project, a Behind Schedule Performance Index (BSPI) that excludes an ahead of schedule component from a scheduled performance index (SPI) associated with said project, said ahead of schedule component being a first component of a schedule variance (SV) associated with said project; means for generating, by said computing application, an ahead/behind trend graph having a first plurality of graphical indicators of ahead of schedule values associated with said project and a second plurality of graphical indicators of behind schedule values associated with said project, wherein said first plurality of graphical indicators and said second plurality of graphical indicators indicate that a portion of said project is behind schedule while said project, as a whole, is ahead of schedule; means for generating, by said computing application, a behind schedule exception report that includes a first set of one or more tasks of said project that are behind schedule based on a baseline of said project and that excludes any task of said project that is ahead of schedule based on said baseline; and means for generating, by said computing application, an ahead of schedule exception report that includes a second set of one or more tasks of said project that are ahead of schedule based on said baseline and that excludes any task of said project that is behind schedule based on said baseline. - View Dependent Claims (9, 10, 11, 12, 13)
-
-
14. A process for supporting computing infrastructure, said process comprising providing at least one support service for at least one of creating, integrating, hosting, maintaining, and deploying computer-readable code in a computing system, wherein the code in combination with the computing system is capable of performing a method of assessing schedule performance of a project, said method comprising:
-
generating, by a computing application capable of managing said project, a Behind Schedule Performance Index (BSPI) that excludes an ahead of schedule component from a scheduled performance index (SPI) associated with said project, said ahead of schedule component being a first component of a schedule variance (SV) associated with said project; generating, by said computing application, an ahead/behind trend graph having a first plurality of graphical indicators of ahead of schedule values associated with said project and a second plurality of graphical indicators of behind schedule values associated with said project, wherein said first plurality of graphical indicators and said second plurality of graphical indicators indicate that a portion of said project is behind schedule while said project, as a whole, is ahead of schedule; generating, by said computing application, a behind schedule exception report that includes a first set of one or more tasks of said project that are behind schedule based on a baseline of said project and that excludes any task of said project that is ahead of schedule based on said baseline; and generating, by said computing application, an ahead of schedule exception report that includes a second set of one or more tasks of said project that are ahead of schedule based on said baseline and that excludes any task of said project that is behind schedule based on said baseline. - View Dependent Claims (15, 16, 17, 18, 19)
-
-
20. A computer-implemented method of validating a task of a project, comprising one of:
-
identifying, by a computing application capable of managing said project, a milestone flag for work error associated with whether said task is a milestone, said identifying said milestone flag for work error facilitating at least one of a validation of a milestone of said project and an analysis of a date conflict associated with said task, wherein said identifying said milestone flag for work error comprises; determining that a milestone flag associated with said task indicates that said task is not a milestone, determining that a work value associated with said task is equal to a zero amount of work, determining that a baseline work value associated with said task is equal to a zero amount of baseline work, and determining that a summary task flag associated with said task indicates that said task is not a summary task; identifying, by said computing application, a work error to facilitate at least one of a validation of said task and said analysis of said date conflict, wherein said task is one of;
said milestone, a key milestone, a deliverable, a dependency, a major dependency, and a key work product, and wherein said identifying said work error comprises;determining that said milestone flag indicates that said task is a milestone, and determining that said work value is not equal to a zero amount of work; and identifying, by said computing application, a missing data for a milestone error to facilitate said analysis of said date conflict, wherein said identifying said missing data for a milestone error comprises one of; determining that a completed task value indicates that said task is completed and an actual finish date field value associated with said task is not equal to an actual finish date associated with said task, and determining that said completed task value indicates that said task is not completed and said actual finish date field value is equal to said actual finish date associated with said task.
-
Specification