System to resolve scheduling constraints
First Claim
1. A method, comprising:
- associating a first activity of a group of activities with a first resource, a first start time on the first resource, and a first end time on the first resource;
associating a second activity of the group of activities with a second resource, a second start time on the second resource, and a second end time on the second resource; and
resolving a maximum constraint of the first activity and a maximum constraint of the second activity after the association of the first activity with the first resource and the association of the second activity with the second resource.
2 Assignments
0 Petitions
Accused Products
Abstract
A system may associate a first activity of a group of activities with a first resource, a first start time on the first resource, and a first end time on the first resource, associate a second activity of the group of activities with a second resource, a second start time on the second resource, and a second end time on the second resource, and resolve a maximum constraint of the first activity and a maximum constraint of the second activity after the association of the first activity with the first resource and the association of the second activity with the second resource. Further aspects may include determination of one or more maximum constraints of the first activity, determination of one or more maximum constraints of the second activity, and determination that at least one of the one or more maximum constraints of the first activity and the one or more maximum constraints of the second activity should be resolved after the association of the first activity with the first resource and before the association of the second activity with the second resource.
9 Citations
21 Claims
-
1. A method, comprising:
-
associating a first activity of a group of activities with a first resource, a first start time on the first resource, and a first end time on the first resource; associating a second activity of the group of activities with a second resource, a second start time on the second resource, and a second end time on the second resource; and resolving a maximum constraint of the first activity and a maximum constraint of the second activity after the association of the first activity with the first resource and the association of the second activity with the second resource. - View Dependent Claims (2, 3, 4, 5, 6, 7, 12, 13)
-
-
8. A computer-readable medium storing program code, the program code comprising:
-
code to associate a first activity of a group of activities with a first resource, a first start time on the first resource, and a first end time on the first resource; code to associate a second activity of the group of activities with a second resource, a second start time on the second resource, and a second end time on the second resource; and code to resolve a maximum constraint of the first activity and a maximum constraint of the second activity after the association of the first activity with the first resource and the association of the second activity with the second resource. - View Dependent Claims (9, 10, 11, 14)
-
-
15. A system comprising:
-
a database of transactional objects stored in main memory, the database comprising activity objects, order objects and resource objects; a database procedure in communication with the database, the database procedure to; associate a first activity of a group of activities with a first resource, a first start time on the first resource, and a first end time on the first resource; associate a second activity of the group of activities with a second resource, a second start time on the second resource, and a second end time on the second resource; and resolve a maximum constraint of the first activity and a maximum constraint of the second activity after the association of the first activity with the first resource and the association of the second activity with the second resource. - View Dependent Claims (16, 17, 18, 19, 20, 21)
-
Specification