METHOD AND SYSTEM FOR MANAGING RESOURCE CONNECTIONS
First Claim
Patent Images
1. A method comprising:
- receiving a user request associated with a centralized resource;
determining availability of a connection to the centralized resource;
determining a stagger delay for connection creation, the stagger delay defining a delay for creation of a new connection;
creating the new connection to the centralized resource based on to the determining availability of the connection and the stagger delay; and
utilizing the new connection to process the user request.
2 Assignments
0 Petitions
Accused Products
Abstract
Methods and system for managing resource connections are described. In one embodiment, a user request associated with a centralized resource may be received. Availability of a connection to the centralized resource may be determined. A stagger delay for connection creation may be determined. The stagger delay may define a delay for creation of a new connection. The new connection to the centralized resource may be created based on the determining of whether the connection to the centralized resource is available and the delay interval. The new connection may be utilized to process the user request.
-
Citations
20 Claims
-
1. A method comprising:
-
receiving a user request associated with a centralized resource; determining availability of a connection to the centralized resource; determining a stagger delay for connection creation, the stagger delay defining a delay for creation of a new connection; creating the new connection to the centralized resource based on to the determining availability of the connection and the stagger delay; and utilizing the new connection to process the user request. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14)
-
-
15. A machine-readable medium comprising instructions, which when implemented by one or more processors perform the following operations:
-
receive a user request associated with a centralized resource; determine availability of a connection to the centralized resource; determine a stagger delay for connection creation, the stagger interval defining a delay for creation of a new connection; create the new connection to the centralized resource based on the determining of whether the connection to the centralized resource is available and the stagger interval; and utilize the new connection to process the user request. - View Dependent Claims (16, 17)
-
-
18. A system comprising:
-
a user request receiver module to receive a user request associated with a centralized resource; an availability determination module to determine availability of a connection to the centralized resource; a stagger delay determination module to determine a stagger delay for connection creation, the stagger delay defining a delay for creation of a new connection; a connection creation module to create the new connection to the centralized resource based on the determining of whether the connection to the centralized resource is available and the stagger interval; and a connection utilization module to utilize the new connection to process the user request. - View Dependent Claims (19, 20)
-
Specification