Waste Disposal During Pit Mining
First Claim
Patent Images
1. A method of open pit mining with waste dumping, comprising:
- extracting material from the open pit and determining whether the material is sent to any one or more of stockpiling, waste and processing;
defining a road network interconnecting a plurality of zones;
determining waste movement along the network from its origin being the zone in which the waste was produced to a destination being the zone in which the waste is to be dumped, to provide a joint extraction and waste movement strategy which optimises the net value of a joint extraction and waste movement schedule; and
each zone containing a plurality of blocks, material extracted from one of the blocks in a zone being sent to a predetermined entry point on the road network, moving the material across the network and depositing the waste material in at least one external waste dump, and some of the waste material being moved on the road network to terminate at one of the zones within the pit, and allocating the material moved to one of the zones within the pit proportionally to an in pit waste dump defined by a refill aggregate that overlaps with that zone, the refill aggregate being a space formed after extraction of material from that aggregate and therefore cleared of original material and after any refill aggregate which sits below that aggregate has been completely refilled.
1 Assignment
0 Petitions
Accused Products
Abstract
A method, apparatus and computer program for pit mining with waste dumping is disclosed, in which material is extracted from an open pit and some of that material is sent to waste. The method optimises a joint extraction and waste refill schedule.
7 Citations
14 Claims
-
1. A method of open pit mining with waste dumping, comprising:
-
extracting material from the open pit and determining whether the material is sent to any one or more of stockpiling, waste and processing; defining a road network interconnecting a plurality of zones; determining waste movement along the network from its origin being the zone in which the waste was produced to a destination being the zone in which the waste is to be dumped, to provide a joint extraction and waste movement strategy which optimises the net value of a joint extraction and waste movement schedule; and each zone containing a plurality of blocks, material extracted from one of the blocks in a zone being sent to a predetermined entry point on the road network, moving the material across the network and depositing the waste material in at least one external waste dump, and some of the waste material being moved on the road network to terminate at one of the zones within the pit, and allocating the material moved to one of the zones within the pit proportionally to an in pit waste dump defined by a refill aggregate that overlaps with that zone, the refill aggregate being a space formed after extraction of material from that aggregate and therefore cleared of original material and after any refill aggregate which sits below that aggregate has been completely refilled. - View Dependent Claims (2)
-
-
3. A method of open pit mining with waste dumping, comprising:
-
extracting material from an open pit and determining some proportion of the extracted material to go to waste; defining a road network having a plurality of nodes, at least some of the nodes defining entry points to a plurality of waste dumps, and wherein the waste dumps are selected from the group of at least one in pit waste dump and at least one external waste dump; and moving the material to go to waste along the network of roadways from a location in the pit to an entry node relating to one of the waste dumps and depositing the material to go to waste at the waste dump, to provide a joint extraction and waste movement strategy which optimises the net value of a joint extraction and waste movement schedule. - View Dependent Claims (4, 5, 6, 7, 8, 9, 10)
-
-
11. An apparatus for scheduling open pit mining with waste dumping, wherein material is extracted from an open pit and a determination is made that some proportion of the extracted material is to go to waste, a road network is provided having a plurality of nodes, at least some of the nodes defining entry points to a plurality of waste dumps, and wherein the waste dumps are selected from the group of at least one in pit waste dump and at least one external waste dump, and material to go to waste is moved along the network of roadways from a location in the pit to an entry node relating to one of the waste dumps and depositing the material to go to waste at the waste dump, the apparatus comprising:
a processor for dividing the pit into a plurality of zones, and for allocating the material to be moved to one of the zones within the pit proportionally to an in pit waste dump defined by a refill aggregate that overlaps with that zone, the refill aggregate being a space formed after extraction of material from that aggregate and therefore cleared of original material and after any refill aggregate which sits below that aggregate has been completely refilled, to thereby provide a joint extraction and waste movement strategy which optimises the net value of a joint extraction and waste movement schedule.
-
12. A computer program for scheduling open pit mining with waste dumping, wherein material is extracted from an open pit and some proportion of the extracted material is to go to waste, comprising:
-
code for defining a road network having a plurality of nodes, at least some of the nodes defining entry points to a plurality of waste dumps, and wherein the waste dumps are selected from the group of at least one in pit waste dump and at least one external waste dump, so material to go to waste is moved along the network of roadways from a location in the pit to an entry node relating to one of the waste dumps and depositing the material to go to waste at the waste dump; code for dividing the pit into a plurality of zones, each zone containing a plurality of blocks so material extracted from one of the blocks in a zone is sent to a predetermined entry point on the road network and moved across the network and deposited at at least one external waste dump, and some is sent on the road network to terminate at one of the zones within the pit; and code for allocating the material moved to one of the zones within the pit proportionally to an in pit waste dump defined by a refill aggregate that overlaps with that zone, the refill aggregate being a space formed after extraction of material from that aggregate and therefore cleared of original material and after any refill aggregate which sits below that aggregate has been completely refilled, to thereby provide a joint extraction and waste movement strategy which optimises the net value of a joint extraction and waste movement schedule. - View Dependent Claims (13, 14)
-
Specification