Charge Bucket Loading for Electric ARC Furnace Production
First Claim
1. A method of loading a charge bucket of a metal processing mill with scrap metal in which the scrap metal is sorted by types, the method comprising;
- loading into a truck body a load of scrap metal, where the load is segmented into two or more types of the scrap metal distributed between a front and back of the truck body;
transporting the load of scrap metal to the charge bucket; and
ejecting the load of scrap metal from the truck and into the charge bucket by pushing the load along a floor of the truck body so that the segments of the load spill over a rear edge of the body in sequence and into the charge bucket, thereby transforming each of the segments into a layer of a type of the scrap metal contained by the charge bucket.
0 Assignments
0 Petitions
Accused Products
Abstract
Loads carried by a haulage vehicle are transferred from the vehicle to a container in a manner that maintains an ordered segmentation of materials comprising each of the loads, where each segment comprises a different type of material. The container receives the load such that each segment forms a layer in the container, which in the case of a charge bucket for feeding an electric arc furnace creates a layering of the different types of material according to a desired recipe for melting scrap metal processed by the mill incorporating the furnace. The transferring of the load is implemented by a haulage truck having a rear eject body whose ejector blade pushes the segmented load out and into the container.
108 Citations
15 Claims
-
1. A method of loading a charge bucket of a metal processing mill with scrap metal in which the scrap metal is sorted by types, the method comprising;
-
loading into a truck body a load of scrap metal, where the load is segmented into two or more types of the scrap metal distributed between a front and back of the truck body; transporting the load of scrap metal to the charge bucket; and ejecting the load of scrap metal from the truck and into the charge bucket by pushing the load along a floor of the truck body so that the segments of the load spill over a rear edge of the body in sequence and into the charge bucket, thereby transforming each of the segments into a layer of a type of the scrap metal contained by the charge bucket. - View Dependent Claims (2, 3, 4, 5, 6, 8, 9)
-
-
7. In a rear eject body for a truck for receiving a load of scrap metal to be transferred to a charge bucket for a furnace of a metal mill, an ejector blade moving between retracted and extended positions for pushing the scrap metal out of the body and a tailgate for moving between open and closed positions, a method of transferring the load from the rear eject body to the charge bucket, the method comprising;
-
with the tailgate in the closed position and the ejector blade retracted, loading into the rear eject body different types of the scrap metal so as to segregate each type along a length of the body, where the segments are ordered along the length in accordance with a recipe for loading the charge bucket; transporting the load comprising the segments of different types of scrap metal to a location of the charge bucket, where a top of the charge bucket is at an elevation below a floor of the rear eject body; and ejecting the load of scrap metal from the rear eject body and into the charge bucket by moving the ejector blade from the retracted position to the extended position and moving the tailgate from the closed position to the open position so as to push the load along the rear eject body without any substantial mixing of the segments, allowing the segments of the load to individually spill over a rear edge of the rear eject body and into the charge bucket so that each segment redistributes itself in the charge bucket to form a layer of the type of scrap metal comprising the segment. - View Dependent Claims (10, 11)
-
-
12. Using a rear eject body of a truck for loading scrap metal into a charge bucket for a furnace of a metal mill, a method of loading the charge bucket comprising an ejector blade moving between retracted and extended positions for pushing the scrap metal out of the body and a tailgate for moving between open and closed positions, a method of loading the charge bucket with the scrap metal, the method comprising:
-
loading the rear eject body with scrap metal so that different types of scrap metal are distributed along a floor of the body from front to back of the body in accordance with a recipe for layering types of scrap metal in the charge bucket; transporting the loaded rear eject body to a charge bucket located within a melt shop of the metal mill; moving an ejector blade of the rear eject body toward a rear edge of the body and in concert with opening the tailgate so as to eject the load of scrap metal into the charge bucket by spilling the scrap metal over the rear edge and into the charge bucket, thereby substantially maintaining the distribution of the different types of scrap metal loaded onto the rear eject body and reorienting the distribution from a substantially vertical distribution in the rear eject body to a layering of each type of scrap metal in the charge bucket such that an ordering of the layering conforms to the recipe for layering types of scrap metal in the charge bucket. - View Dependent Claims (13, 14, 15)
-