Systems and Methods for Project Management Task Prioritization
First Claim
1. A method of determining prioritization factors for tasks in a project comprising at least a first task and a second task, the method comprising:
- providing an initial order for performing the tasks in the project, the initial order specifying the first task being performed ahead of the second task;
receiving inputs to change the order for performing the tasks to move the second task ahead of the first task;
determining a relative priority of the first and second tasks based on said inputs; and
updating the prioritization factors for the first and second tasks.
1 Assignment
0 Petitions
Accused Products
Abstract
A project management task prioritization system is provided to refine the prioritization factors for tasks in a project based on changes to the order of performing the tasks. The initial proposed order for performing the tasks is provided by the system to the person responsible for the task in a graphical format that allows the person to drag and drop the tasks, adjusting the order of the tasks to their preferred order. A neural network comparator is used to compare the task prioritization factors associated with each pair of tasks that are altered in order to determine a relative priority. The neural network system updates the task prioritization factors based on the changes in order the tasks are to be performed.
112 Citations
19 Claims
-
1. A method of determining prioritization factors for tasks in a project comprising at least a first task and a second task, the method comprising:
-
providing an initial order for performing the tasks in the project, the initial order specifying the first task being performed ahead of the second task; receiving inputs to change the order for performing the tasks to move the second task ahead of the first task; determining a relative priority of the first and second tasks based on said inputs; and updating the prioritization factors for the first and second tasks. - View Dependent Claims (2, 3, 4, 5, 6, 7)
-
-
8. A software product comprising a machine readable medium including a program of instructions for determining prioritization factors for tasks in a project comprising at least a first task and a second task, wherein the program of instructions upon being executed on a device causes the device to perform activities comprising:
-
providing an initial order for performing the tasks in the project, the initial order specifying the first task being performed ahead of the second task; receiving inputs to change the order for performing the tasks to move the second task ahead of the first task; determining a relative priority of the first and second tasks based on said inputs; and updating the prioritization factors for the first and second tasks. - View Dependent Claims (9, 10, 11, 12, 13, 14)
-
-
15. A system configured to determine prioritization factors for tasks in a project comprising at least a first task and a second task, the system comprising:
-
an electronically readable storage medium configured to store an initial order for performing the tasks in the project, the initial order specifying the first task being performed ahead of the second task; a display device configured to display the initial order of the tasks in the project; means for receiving inputs to change the order for performing the tasks to move the second task ahead of the first task; a processor configured to execute instructions to determine a relative priority of the first and second tasks based on said inputs, the processor further being configured to update the prioritization factors for the first and second tasks. - View Dependent Claims (16, 17, 18, 19)
-