Method and Apparatus for Plasma Process Performance Matching in Multiple Wafer Chambers

  • US 20090206056A1
  • Filed: 02/06/2009
  • Published: 08/20/2009
  • Est. Priority Date: 02/14/2008
  • Status: Abandoned Application
First Claim
Patent Images

1. In a multi-station workpiece processing system having a single chamber including at least two processing stations for simultaneously processing two or more workpieces with one workpiece located at each station, a method for processing at least one workpiece at one active one of the processing stations with at least one other one of the processing stations inactive, each of said processing stations including a plasma generator that receives a processing station gas supply for use in generating a plasma to treat a particular workpiece at that processing station, and wherein at least a portion of said processing station gas supply, that is released in the plasma generator at a given one of the processing stations, is capable of flowing, as a cross-flow, to at least one other one of the processing stations through the chamber arrangement, irrespective of whether the given processing station is active or inactive, said system further being configured for producing a full workload gas flow that is distributed to all the processing stations from an overall gas input to produce said processing station gas supply for the plasma generator of each processing station such that each processing station receives, at least approximately, a target equal share of the full workload gas flow, as said processing station gas supply, when all of the processing stations are active, said method comprising:

  • selecting less than said total number of processing stations as active processing stations such that at least one processing station is selected to actively process a workpiece while at least one other one of the processing stations is inactive and does not process a workpiece;

    terminating the gas supply to the inactive process stations;

    corresponding to each inactive processing station, reducing the full workload gas flow by an amount that is approximately equal to the full workload gas flow divided by the total number of processing stations to produce a current gas flow, at the overall gas input, that is distributed among the active processing stations such that each active processing station receives, at least approximately, said target equal share of the current gas flow, irrespective of the inactive processing stations, and said cross-flow from inactive ones of the processing stations to active ones of the processing stations is eliminated such that a cross-flow related process influence at the active processing stations, which would otherwise be produced by emitting the processing station gas supply at the inactive processing stations, is eliminated. This eliminates the need for separate sets of flow controllers to each process station.

View all claims
  • 1 Assignment
Timeline View
Assignment View
    ×
    ×