PROCESS FOR COLLECTING OPERATIONAL AND CONDITIONAL INFORMATION ON INFRASTRUCTURES AND FOR RELATED PRIORITY SETTING
First Claim
Patent Images
1. A computerized process for determining capital outlay, the steps comprising:
- setting a priority and cost factor for a plurality of capital projects related to a railway system in an electronic database;
applying a risk factor to each of the plurality of capital projects maintained by the electronic database; and
determining a capital budget for the plurality of capital projects based on the priority, cost, and applied risk and performing at least one capital project based on the determined budget,wherein the setting, applying, determining steps are executed on a computer processing platform.
1 Assignment
0 Petitions
Accused Products
Abstract
A process and system to collect operational and conditional information on infrastructure such as railroads or pipelines, for example, is disclosed. The process includes techniques for organizing, sorting, evaluating and selecting capital investments in the infrastructure, including identification of higher risk for maintenance, and in the case of railroads for derailments, even though a specific location or portion of infrastructure may not have been identified for evaluation.
16 Citations
15 Claims
-
1. A computerized process for determining capital outlay, the steps comprising:
-
setting a priority and cost factor for a plurality of capital projects related to a railway system in an electronic database; applying a risk factor to each of the plurality of capital projects maintained by the electronic database; and determining a capital budget for the plurality of capital projects based on the priority, cost, and applied risk and performing at least one capital project based on the determined budget, wherein the setting, applying, determining steps are executed on a computer processing platform. - View Dependent Claims (2, 3, 4, 5)
-
-
6. A system for maintaining a rail system, comprising:
-
a computerized asset management system that includes a bridge management subsystem to manage bridge inventory and incidents associated with bridges, a crossing diamond subsystem to manage crossing diamond inventory and condition status of crossing diamonds, a curve management subsystem to track curve inventory and curve condition data, a master track and chain feet subsystem to maintain data related to master tracks, a road crossing subsystem to maintain data related to road crossing inventory and road crossing incidents, and a roadway machines subsystem to provide lifecycle management of maintenance of way work equipment; and a computerized reporting system that includes a geometry exceptions subsystem that maintains and provides priority exceptions for one or more aspects of the rail system maintained at least in part by the asset managing system, wherein the computerized asset management system and computerized reporting system facilitate management of a rail system. - View Dependent Claims (7, 8, 9, 10)
-
-
11. A computer program product embodied in a computer readable medium that is accessible for execution, the computer program product includes machine executable instructions that when executed causes the execution of steps for determining capital outlay for a infrastructure system, the computer program product comprises:
-
a first component to set a priority and cost factor for a plurality of capital projects related to a railway system in an electronic database; a second component to apply a risk factor to each of the plurality of capital projects maintained by the electronic database; and a third component to determine a capital budget for the plurality of capital projects based on the priority, cost, and applied risk and performing at least one capital project based on the determined budget. - View Dependent Claims (12, 13, 14, 15)
-
Specification