Bulk Material Ship Routing and Inventory Management Schedule Optimization
First Claim
1. A method to plan and schedule bulk material distribution for the transportation of bulk materials from supply terminals to demand terminals so that the supply terminals do not have an over-supply and the demand terminals do not have an undersupply comprising:
- a) obtaining input data specifying the requirements to be satisfied for the marine transportation schedule to meet predetermined objectives,b) determining a feasible schedule from said input data,c) evaluating said feasible schedule to determine how well the schedule meets the predetermined objectives, andd) iterating the feasible schedule by adjusting the input data to minimize deviations from the predetermined objectives.
1 Assignment
0 Petitions
Accused Products
Abstract
The present invention is a computational system to generate feasible marine transportation schedules given a proposed bulk material supply chain. The decision support tool will fulfill the objectives and scope defined above. The technology employed will require (a) the use of mathematical programming modeling techniques (mixed integer linear programming) to mathematically formulate the business problem, and (b) advanced proprietary solution methods to produce solutions satisfying all constraints of the mathematical model while optimizing an objective function. The decision support tool has the following capabilities: Read input data, Generate feasible bulk material ship Schedule, Evaluate bulk material ship Schedule with User-defined Objective Function, Allow Case comparison, Graphical user interface (GUI) for specifying input data and displaying results.
-
Citations
11 Claims
-
1. A method to plan and schedule bulk material distribution for the transportation of bulk materials from supply terminals to demand terminals so that the supply terminals do not have an over-supply and the demand terminals do not have an undersupply comprising:
-
a) obtaining input data specifying the requirements to be satisfied for the marine transportation schedule to meet predetermined objectives, b) determining a feasible schedule from said input data, c) evaluating said feasible schedule to determine how well the schedule meets the predetermined objectives, and d) iterating the feasible schedule by adjusting the input data to minimize deviations from the predetermined objectives. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8)
-
-
9. A system for planning and scheduling bulk material distribution and transportation comprising:
-
a) a schedule generator for generating a schedule b) a schedule evaluator c) a case management system for storing the schedule d) means for iterating the schedule
-
-
10. A method to determine marine transportation schedules for the transportation of liquid natural gas (LNG) from LNG terminals to Re-gasification terminals so that LNG terminals do not have an over-supply and Re-gasification terminals do not have an undersupply of LNG comprising:
-
a) obtaining input data specifying the requirements to be satisfied for the marine transportation schedule to meet predetermined objectives, b) determining a feasible schedule from said input data by optimizing the predetermined objectives. c) evaluating said feasible schedule to determine how well the schedule meets the predetermined objectives, and d) iterating the feasible schedule by adjusting the input data to minimize deviations from the predetermined objectives.
-
-
11. A method to generate feasible ship schedules among LNG terminals by:
-
a) generating minimum set of travel choices by eliminating infeasible choices from the time-space network, b) assigning initial voyage to each ship among terminals, c) improving ship schedule in a sub-network iteratively by reducing the number of ships in the time-space network.
-
Specification