CONSTRUCTION COST ESTIMATING AND SCHEDULING SYSTEM AND METHOD
First Claim
1. A system for determining an escalated estimated project cost and an estimated schedule for a project including a plurality of activities, the system comprising:
- a computer system having specialized programming for determining said escalated estimated cost and said estimated schedule for said project, based on said plurality of activities;
said computer system having means to receive an input from a user of said plurality of activities for said project, each activity having one or more cost items, and each activity including a number of days for completion, or information sufficient to compute said number of days for completion;
said computer system being operable to receive an input from said user of a start date of said project and, for each activity, an input of an amount of critical days to include on a critical path of said project out of said number of days for completion for each activity;
said computer system being operable to determine a critical path for said project based on said amount of critical days to include on said critical path for each activity;
said computer system being operable to determine a start date and a finish date for each activity based on said critical path;
said computer system being operable to determine a pre-escalation cost for each cost item of each activity, and to determine a pre-escalation cost for each activity by summing said pre-escalation costs for each cost item in each activity;
said computer system being operable to determine a pre-escalation total project cost by summing said pre-escalation cost for each activity;
said computer system being operable to determine a cost escalation for each activity;
said computer being operable to determine a cost escalation for said project by summing said cost escalation for each activity, and being operable to determine an escalated estimated cost of said project by summing said pre-escalation total project cost and said cost escalation for said project;
said computer system being operable to generate a report of said pre-escalation total project cost and said escalated estimated project cost; and
said computer system being operable to generate said estimated project schedule based on said critical path, as determined by the computer system.
1 Assignment
0 Petitions
Accused Products
Abstract
A computer system for determining an escalated estimated project cost and an estimated schedule for a project including a plurality of activities having a plurality of cost items. The computer system is operable to determine: a critical path for the project based on the amount of critical days to include on the critical path for each activity, a pre-escalation cost for each cost item of each activity, a pre-escalation cost for each activity, a pre-escalation total project cost, a cost escalation for each activity, a cost escalation for the project, and an escalated estimated cost of the project, and the computer system is operable to generate a report of the pre-escalation total project cost, the escalated estimated project cost, and the estimated project schedule based on the critical path.
-
Citations
6 Claims
-
1. A system for determining an escalated estimated project cost and an estimated schedule for a project including a plurality of activities, the system comprising:
-
a computer system having specialized programming for determining said escalated estimated cost and said estimated schedule for said project, based on said plurality of activities; said computer system having means to receive an input from a user of said plurality of activities for said project, each activity having one or more cost items, and each activity including a number of days for completion, or information sufficient to compute said number of days for completion; said computer system being operable to receive an input from said user of a start date of said project and, for each activity, an input of an amount of critical days to include on a critical path of said project out of said number of days for completion for each activity; said computer system being operable to determine a critical path for said project based on said amount of critical days to include on said critical path for each activity; said computer system being operable to determine a start date and a finish date for each activity based on said critical path; said computer system being operable to determine a pre-escalation cost for each cost item of each activity, and to determine a pre-escalation cost for each activity by summing said pre-escalation costs for each cost item in each activity; said computer system being operable to determine a pre-escalation total project cost by summing said pre-escalation cost for each activity; said computer system being operable to determine a cost escalation for each activity; said computer being operable to determine a cost escalation for said project by summing said cost escalation for each activity, and being operable to determine an escalated estimated cost of said project by summing said pre-escalation total project cost and said cost escalation for said project; said computer system being operable to generate a report of said pre-escalation total project cost and said escalated estimated project cost; and said computer system being operable to generate said estimated project schedule based on said critical path, as determined by the computer system. - View Dependent Claims (2, 3, 4, 5, 6)
-
Specification