×

CONSTRUCTION COST ESTIMATING AND SCHEDULING SYSTEM AND METHOD

  • US 20100088240A1
  • Filed: 07/01/2009
  • Published: 04/08/2010
  • Est. Priority Date: 07/01/2008
  • Status: Abandoned Application
First Claim
Patent Images

1. A system for determining an escalated estimated project cost and an estimated schedule for a project including a plurality of activities, the system comprising:

  • a computer system having specialized programming for determining said escalated estimated cost and said estimated schedule for said project, based on said plurality of activities;

    said computer system having means to receive an input from a user of said plurality of activities for said project, each activity having one or more cost items, and each activity including a number of days for completion, or information sufficient to compute said number of days for completion;

    said computer system being operable to receive an input from said user of a start date of said project and, for each activity, an input of an amount of critical days to include on a critical path of said project out of said number of days for completion for each activity;

    said computer system being operable to determine a critical path for said project based on said amount of critical days to include on said critical path for each activity;

    said computer system being operable to determine a start date and a finish date for each activity based on said critical path;

    said computer system being operable to determine a pre-escalation cost for each cost item of each activity, and to determine a pre-escalation cost for each activity by summing said pre-escalation costs for each cost item in each activity;

    said computer system being operable to determine a pre-escalation total project cost by summing said pre-escalation cost for each activity;

    said computer system being operable to determine a cost escalation for each activity;

    said computer being operable to determine a cost escalation for said project by summing said cost escalation for each activity, and being operable to determine an escalated estimated cost of said project by summing said pre-escalation total project cost and said cost escalation for said project;

    said computer system being operable to generate a report of said pre-escalation total project cost and said escalated estimated project cost; and

    said computer system being operable to generate said estimated project schedule based on said critical path, as determined by the computer system.

View all claims
  • 1 Assignment
Timeline View
Assignment View
    ×
    ×