1. A method of deploying a production tree, comprising:
- (a) providing a modular production tree assembly having a plurality of modules, including an upper tree module, a lower tree module, and a choke bridge module;
(b) assembling the upper tree module, lower tree module, and choke bridge module on land and testing the modular production tree assembly;
(c) transporting the modular production tree assembly to an offshore rig;
(d) separately lifting the upper tree module, lower tree module, and choke bridge module onto the offshore rig with a first crane mounted to the offshore rig;
(e) reassembling the upper tree module, lower tree module and choke bridge module into the modular production tree assembly;
(f) performing only interface testing between the upper tree module, lower tree module and choke bridge module; and
then(g) deploying the modular production tree assembly to the sea floor with a second crane mounted to the offshore rig.
1 Assignment
0 Petitions
Accused Products
Abstract
A modular tree production tree assembly reduces the weight during transfer of the tree components from a barge to a production rig. The tree assembly includes an upper tree module, a lower tree module, and a choke bridge module. The upper tree module has a tree head, the lower tree module has a guidance system and ties in the flow lines to the in-field infrastructure, and the choke bridge module has the choke and instrumentation bridge to link the three components together. Prior to delivery to the rig, the components of the modular tree assembly may be joined together and tested on shore. Upon arrival at the rig, the components are individually lifted from the barge onto the rig by a crane. After the tree components are on the rig, the modular tree is reassembled and then deployed to the sea floor via the draw works.
-
Citations
19 Claims
-
1. A method of deploying a production tree, comprising:
-
(a) providing a modular production tree assembly having a plurality of modules, including an upper tree module, a lower tree module, and a choke bridge module; (b) assembling the upper tree module, lower tree module, and choke bridge module on land and testing the modular production tree assembly; (c) transporting the modular production tree assembly to an offshore rig; (d) separately lifting the upper tree module, lower tree module, and choke bridge module onto the offshore rig with a first crane mounted to the offshore rig; (e) reassembling the upper tree module, lower tree module and choke bridge module into the modular production tree assembly; (f) performing only interface testing between the upper tree module, lower tree module and choke bridge module; and
then(g) deploying the modular production tree assembly to the sea floor with a second crane mounted to the offshore rig. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8)
-
-
9. A method of deploying a production tree, comprising:
-
(a) providing a modular production tree assembly having three modules, consisting of an upper tree module, a lower tree module, and a choke bridge module; (b) assembling the upper tree module, lower tree module, and choke bridge module on land and testing the modular production tree assembly; (c) transporting the modular production tree assembly to an offshore rig; (d) disassembling the modular production tree assembly and separately lifting the upper tree module, lower tree module, and choke bridge module onto the offshore rig with a first crane mounted to the offshore rig; (e) reassembling the upper tree module, lower tree module and choke bridge module into the modular production tree assembly on the offshore rig; (f) performing only interface testing between the upper tree module, lower tree module and choke bridge module; and
then(g) deploying the modular production tree assembly to the sea floor with a second crane mounted to the offshore rig. - View Dependent Claims (10, 11, 12, 13, 14, 15, 16)
-
-
17. A method of deploying a production tree, comprising:
-
(a) providing a modular production tree assembly having three modules, consisting of an upper tree module, a lower tree module, and a choke bridge module, the upper tree module comprising a tree head and a subsea control system, the lower tree module comprising a guidance system, counterweights, a cathodic protection system, and means for tying in flow lines to an in-field infrastructure, and the choke bridge module comprising a choke and instrumentation bridge to link together the upper tree module, lower tree module, and choke bridge module; (b) assembling the upper tree module, lower tree module, and choke bridge module on land and testing the modular production tree assembly; (c) transporting the modular production tree assembly to an offshore rig; (d) disassembling the modular production tree assembly and separately lifting the upper tree module, lower tree module, and choke bridge module onto the offshore rig with an outrigger crane mounted to the offshore rig; (e) reassembling the upper tree module, lower tree module and choke bridge module into the modular production tree assembly on the offshore rig; (f) performing only interface testing between the upper tree module, lower tree module and choke bridge module; and
then(g) deploying the modular production tree assembly to the sea floor with a draw works mounted to the offshore rig. - View Dependent Claims (18, 19)
-