APPARATUS OF ANALIZING THE CONSTRUCTION PRODUCTIVITY USING RFID BASED ON THE WIRELESS COMMUNICATION AND THEREOF
First Claim
1. An apparatus for analyzing construction productivity in real time by using an RFID based on wireless communication, the apparatus comprising:
- an RFID tag including an ID code for identification of each equipment for construction work and attached to each equipment;
a tag data management device for reading the ID code of the RFID tag in order to check a cycle time of each equipment in each process of the construction work, integrating the read time and position of the RFID tag and the ID code of the RFID tag, and transmitting the integrated data;
a central server for receiving the time and position data and the ID code data of the RFID tag from the tag data management device and updating the data in real time to monitor the productivity in real time; and
a database for storing the prestored data and the real-time input data of the central server.
1 Assignment
0 Petitions
Accused Products
Abstract
The present invention relates to a real-time construction productivity analyzing apparatus and method using an RFID based on wireless communication. The present invention provides an apparatus and method that can provide a systematic construction management system through the real-time productivity analysis and the real-time monitoring for each process of the construction field, and can detect a productivity-reducing factor in real time by integrating IT fields such as wireless communication technology and RFID technology, so that the near target productivity can be achieved by prompt treatment.
The real-time construction productivity analyzing apparatus includes: an RFID tag including an ID code for identification of each equipment for construction work and attached to each equipment; a tag data management device for reading the ID code of the RFID tag in order to check a cycle time of each equipment in each process of the construction work, integrating the read time and position of the RFID tag and the ID code data of the RFID tag, and transmitting the integrated data; a central server for receiving the time and position data and the ID code of the RFID tag from the tag data management device and updating the data in real time to monitor the productivity in real time; and a database for storing the prestored data and the real-time input data of the central server.
24 Citations
17 Claims
-
1. An apparatus for analyzing construction productivity in real time by using an RFID based on wireless communication, the apparatus comprising:
-
an RFID tag including an ID code for identification of each equipment for construction work and attached to each equipment; a tag data management device for reading the ID code of the RFID tag in order to check a cycle time of each equipment in each process of the construction work, integrating the read time and position of the RFID tag and the ID code of the RFID tag, and transmitting the integrated data; a central server for receiving the time and position data and the ID code data of the RFID tag from the tag data management device and updating the data in real time to monitor the productivity in real time; and a database for storing the prestored data and the real-time input data of the central server. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12)
-
-
13. A method for analyzing construction productivity in real time by using an RFID based on wireless communication, the method comprising:
-
modeling a cycle time of each equipment in each process of construction work and setting and inputting an optimized cycle time; using an RFID tag and an RFID reader to check the cycle time of the equipment to discriminate between the respective equipments of the construction work; if the RFID reader and a central server receiving data read by the RFID reader are located in the near field, transmitting the data to the central server through a near-field communication unit to update the cycle time of the equipment in real time; and if the cycle time of the equipment is longer than the optimized cycle time, outputting data to eliminate a productivity-reducing factor to optimize the productivity. - View Dependent Claims (14, 15, 16, 17)
-
Specification