TASK HIERARCHY IN AN EVENT-DRIVEN COMMUNICATION SYSTEM

  • US 20100262653A1
  • Filed: 04/09/2010
  • Published: 10/14/2010
  • Est. Priority Date: 04/09/2009
  • Status: Active Grant
First Claim
Patent Images

1. A computer-implemented method for maintaining task hierarchies for multiple projects using a computer server machine having a processor and network connection to a client machine having a computer display, the method comprising:

  • obtaining, using the computer server processor, a user-task list comprising;

    a first-project task having an initial first-project task score, wherein the first-project task is associated with a first-project, the first-project having a first-project task list including the first-project task,a second-project task having an second-project task score, wherein the second-project task is associated with a second-project, the second-project having a second-project task list including the second-project task, andan initial user-task hierarchy ranking the first-project task and second-project task based on the initial first-project task score and the second-project task score;

    obtaining, using the computer server processor, a set of parameters associated with the first-project task;

    determining, using the computer server processor, an updated first-project task score for the first-project task, wherein the updated first-project task score is determined based on the set of parameters;

    determining, using the computer server processor, an updated user-task hierarchy by ranking the first-project task and the second-project task based on the updated first-project task score and the second-project task score; and

    displaying, using the client machine computer display, the user-task list to a user in a format depicting the updated user-task hierarchy.

View all claims
  • 18 Assignments
Timeline View
Assignment View
    ×
    ×