Method for evaluating operational and financial performance for dispatchers using after the fact analysis
First Claim
1. A method for evaluating operational and financial performance for dispatchers in power grid control centers associated with utility systems, comprising:
- providing a comprehensive operating plan that applies after the fact analysis for performance metrics, root-cause impacts and process re-engineering;
applying after the fact analysis of past events and practices; and
capturing actual system and resource conditions;
supplying the system and resource conditions to a relational database, wherein a scheduler engine receives the actual system and resource conditions from the relational database and processes it to calculate system performance; and
displaying at least one of, transmission evaluation application displays, reference and scenario cases and associations between them, results presented with a graphical or tabular displays, comparison results between scenario cases and a reference case, a family of curves where each curve is a performance metric, comparison of scenario input data, study results and statistical analysis and historical data.
3 Assignments
0 Petitions
Accused Products
Abstract
A method is provided for evaluating operational and financial performance for dispatchers in power grid control centers associated with utility systems. A comprehensive operating plan is provided that applies after the fact analysis for performance metrics, root-cause impacts and process re-engineering. after the fact analysis of past events and practices is performed. Actual system and resource conditions are captured. the system and resource conditions are supplied to a relational database. A scheduler engine receives the actual system and resource conditions from the relational database and processes it to calculate system performance. At least one of the following is displayed, transmission evaluation application displays, reference and scenario cases and associations between them, results presented with a graphical or tabular displays, comparison results between scenario cases and a reference case, a family of curves where each curve is a performance metric, comparison of scenario input data, study results and statistical analysis and historical data.
-
Citations
20 Claims
-
1. A method for evaluating operational and financial performance for dispatchers in power grid control centers associated with utility systems, comprising:
-
providing a comprehensive operating plan that applies after the fact analysis for performance metrics, root-cause impacts and process re-engineering; applying after the fact analysis of past events and practices; and capturing actual system and resource conditions; supplying the system and resource conditions to a relational database, wherein a scheduler engine receives the actual system and resource conditions from the relational database and processes it to calculate system performance; and displaying at least one of, transmission evaluation application displays, reference and scenario cases and associations between them, results presented with a graphical or tabular displays, comparison results between scenario cases and a reference case, a family of curves where each curve is a performance metric, comparison of scenario input data, study results and statistical analysis and historical data. - View Dependent Claims (2, 3, 9)
-
-
4. A method for evaluating operational and financial performance for dispatchers in power grid control centers associated with utility systems, comprising:
-
applying after the fact analysis of past events and practices; using after the fact analysis for performance metrics, root-cause impacts and process re-engineering; using quantitative assessments of how specific events and practices effect energy dispatch power grid system performance; and using hypothetical scenario analysis to perform simulation of hypothetical scenarios and evaluate cost deviations. - View Dependent Claims (5, 6, 7, 8)
-
-
10. A method for evaluating operational and financial performance for dispatchers in power grid control centers associated with utility systems, comprising:
-
applying after the fact analysis of past events and practices; and using after the fact analysis for performance metrics, root-cause impacts and process re-engineering, wherein after the fact analysis calculates a hypothetical least bid production cost commitment and dispatch. - View Dependent Claims (11, 12)
-
-
13. A method for evaluating operational and financial performance for dispatchers in power grid control centers associated with utility systems, comprising:
-
applying after the fact analysis of past events and practices; using after the fact analysis for performance metrics, root-cause impacts and process re-engineering; and wherein after the fact analysis calculates cost associated with actual dispatch and compares it against a cost associated with the reference dispatch. - View Dependent Claims (14, 15)
-
-
16. A method for evaluating operational and financial performance for dispatchers in power grid control centers associated with utility systems, comprising:
-
applying after the fact analysis of past events and practices; and using after the fact analysis for performance metrics, root-cause impacts and process re-engineering; and identifying impacts for events and analyzing multiple events within a given after the fact analysis study. - View Dependent Claims (17, 18, 19, 20)
-