1. A system for planning a project, the system comprising:

  • a work detail database having stored therein one or more attributes for the project;

    a schedule generator coupled to receive information from said work detail database and to generate schedules;

    a pull processor coupled to provide to said schedule generator at least one of the one or more precedence constraints together with all attributes of those constraints; and

    a push processor coupled to exchange data with said schedule generator, said push processor including a simulation engine for generating a data flow model comprised of a plurality of precedence actors and a plurality of work detail actors and for simulating a series of activities and resources and for generating a project plan including a schedule of all activities.

View all claims
  • 2 Assignments
Timeline View
Assignment View
    ×
    ×