DEVELOPING AN OPTIMAL LONG TERM ELECTRICITY GENERATION CAPACITY RESOURCE PLAN UNDER A CARBON DIOXIDE REGULATORY REGIME

  • US 20110178833A1
  • Filed: 01/20/2010
  • Published: 07/21/2011
  • Est. Priority Date: 01/20/2010
  • Status: Abandoned Application
First Claim
Patent Images

1. A method for optimizing of a long-term electricity resource plan, the method comprising;

  • receiving a first data for calculating a capital costs component value, the first data including capital costs for emission abatement retrofits at an existing power plant and a new power plant over a period of time;

    receiving a second data for calculating a fuel costs component value, the second data including a sum of fuel utilization of all generating units in the existing power plant and new power plant over the period of time;

    receiving a third data for calculating an emission costs component value, the third data including emission allowance costs and emission violation costs in the period of time; and

    adding the capital costs component value, the fuel costs component value and the emission costs component value to compute a resulting value that meets emission constraints,wherein a program using a processor unit runs one or more of;

    the receiving the first data, the receiving the second data, receiving the third data and the adding.

View all claims
  • 1 Assignment
Timeline View
Assignment View
    ×
    ×