SYSTEM AND METHOD FOR OPERATING A TAP CHANGER
First Claim
Patent Images
1. A method of operating a tap changer of a transformer or a voltage regulator in a power grid comprising:
- obtaining a load forecast for a time period;
determining an average voltage profile for the time period based on the load forecast;
estimating tap positions of the tap changer for leveling the average voltage profile during the time period; and
providing switching signal commands to the tap changer based on the estimated tap positions.
2 Assignments
0 Petitions
Accused Products
Abstract
A method of operating a tap changer of a transformer or a voltage regulator in a power grid includes obtaining a load forecast for a time period. An average voltage profile is determined for the time period based on the load forecast. The method further includes estimating tap positions of the tap changer for leveling the average voltage profile during the time period. Switching signal commands are provided to the tap changer based on the estimated tap positions.
-
Citations
20 Claims
-
1. A method of operating a tap changer of a transformer or a voltage regulator in a power grid comprising:
-
obtaining a load forecast for a time period; determining an average voltage profile for the time period based on the load forecast; estimating tap positions of the tap changer for leveling the average voltage profile during the time period; and providing switching signal commands to the tap changer based on the estimated tap positions. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12)
-
-
13. A tap changer control system comprising:
-
a load forecasting module to determine a load forecast for a time period; a load flow module to determine an average voltage profile for the time period of interest; a tap position identification module to estimate tap positions of a tap changer of a transformer or a voltage regulator for leveling the average voltage profile; and a switching circuitry to adjust taps of the tap changer based on the estimated tap positions. - View Dependent Claims (14, 15, 16, 17, 18, 19)
-
-
20. A computer-readable medium comprising non-transitory computer-readable instructions that, when executed by a processor, cause the processor to perform a method of operating a tap changer of a transformer or a voltage regulator in a power grid, the method comprising:
-
obtaining a load forecast for a time period; determining an average voltage profile for the time period based on the load forecast; estimating tap positions of the tap changer for leveling the average voltage profile during the time period; and providing switching signal commands to tap changer based on the estimated tap positions.
-
Specification