SYSTEM AND METHOD FOR OPTIMIZING PLANT OPERATIONS
First Claim
Patent Images
1. A system comprising:
- a risk calculation system configured to calculate a risk based on a static input and a dynamic input; and
a decision support system configured to use the risk to derive a decision; and
a plant control system configured to update operations of a plant based on the decision, wherein the decision predicts future plant conditions.
2 Assignments
0 Petitions
Accused Products
Abstract
Embodiments of the present disclosure include systems and a method. In one embodiment, a system is provided. The system includes a risk calculation system configured to calculate a risk based on a static input and a dynamic input, and a decision support system configured to use the risk to derive a decision. The system also includes a plant control system configured to update operations of a plant based on the decision, wherein the decision predicts future plant conditions.
154 Citations
22 Claims
-
1. A system comprising:
-
a risk calculation system configured to calculate a risk based on a static input and a dynamic input; and a decision support system configured to use the risk to derive a decision; and a plant control system configured to update operations of a plant based on the decision, wherein the decision predicts future plant conditions. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9)
-
-
10. A method, comprising:
-
determining an occurrence of an event based on an event rule and a dynamic input associated with components of a plant; and responding to the occurrence of the event, if the event occurs, wherein responding comprises; updating a risk projection based on at least one dynamic input; updating a risk threshold based on at least one static input; determining whether the risk projection exceeds the risk threshold; determining a first action if the risk projection exceeds the risk threshold, wherein determining the first action comprises selecting a mitigation action as the first action if one or more mitigation actions are available, or determining a recommended action as the first action if no mitigation actions are available; and determining a second action if the risk projection does not exceed the risk threshold, wherein determining the second action comprises calculating a next scheduled action as the second action. - View Dependent Claims (11, 12, 13, 14, 15, 16, 17, 18, 19)
-
-
20. A system comprising:
a power plant controller configured to receive dynamic inputs and static inputs related to a power plant, wherein the power plant controller is configured to derive a decision impacting power plant operations, the power plant controller is configured to determine when a test of a component of the power plant is recommended based on monitoring the dynamic and static inputs, the power plant controller is configured to identify an occurrence of an event related to the test, and the power plant controller is configured to adjust a test schedule based on a performance of the component during the event. - View Dependent Claims (21, 22)