MANAGEMENT SYSTEM AND MANAGEMENT METHOD
First Claim
1. A management system for creating an inspection schedule of objects to be tested within a plurality of sectioned management areas, the management system comprising:
- a database that stores an inspection time limit and positional information of the objects to be tested;
a calculation unit that calculates the costs for inspecting the objects to be tested on the basis of the positional information; and
a schedule creation unit that creates a schedule for inspecting the objects to be tested on the basis of calculation results,wherein the calculation unit calculates a first cost required when the objects to be tested within the management areas are inspected at the same timing within a first time limit, and a second cost required when a part of the objects to be tested within the management areas is inspected within the first time limit, individually, and the other objects to be tested within the management areas are inspected at the same timing within a second time limit longer than the first time limit, andwherein the schedule creation unit compares the calculated first costs with the calculated second costs, and creates an inspection schedule in which the time limits when the objects to be tested within each of the management areas are inspected are combined with the objects to be tested, individually, on the basis of comparison results.
1 Assignment
0 Petitions
Accused Products
Abstract
A management system for creating an inspection schedule of objects to be tested within a plurality of management areas, includes a calculation unit that calculates the costs for inspecting the objects to be tested based on the positional information; and a schedule creation unit that creates a schedule for inspecting the objects to be tested based on calculation results. The calculation unit calculates a first cost required when the objects to be tested within the management areas are inspected at the same timing within a first time limit, and a second cost required when a part of the objects to be tested within the management areas is inspected within the first time limit, individually, and the other objects to be tested within the management areas are inspected at the same timing within a second time limit longer than the first time limit.
12 Citations
15 Claims
-
1. A management system for creating an inspection schedule of objects to be tested within a plurality of sectioned management areas, the management system comprising:
-
a database that stores an inspection time limit and positional information of the objects to be tested; a calculation unit that calculates the costs for inspecting the objects to be tested on the basis of the positional information; and a schedule creation unit that creates a schedule for inspecting the objects to be tested on the basis of calculation results, wherein the calculation unit calculates a first cost required when the objects to be tested within the management areas are inspected at the same timing within a first time limit, and a second cost required when a part of the objects to be tested within the management areas is inspected within the first time limit, individually, and the other objects to be tested within the management areas are inspected at the same timing within a second time limit longer than the first time limit, and wherein the schedule creation unit compares the calculated first costs with the calculated second costs, and creates an inspection schedule in which the time limits when the objects to be tested within each of the management areas are inspected are combined with the objects to be tested, individually, on the basis of comparison results. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10, 11)
-
-
12. A management method for creating an inspection schedule of objects to be tested within a plurality of sectioned management areas, the management method comprising:
-
a first step of storing an inspection time limit and positional information of the objects to be tested; a second step of calculating a first cost required when the objects to be tested within the management areas are inspected at the same timing within a first time limit, on the basis of the positional information; a third step of calculating a second cost required when a part of the objects to be tested within the management area is inspected in the first time limit, individually, and the other objects to be inspected within the management area are inspected within a second time limit longer than the first time limit at the same timing, on the basis of the positional information; a fourth step of comparing the calculated first cost with the calculated second cost; a fifth step of determining the combination of the time limit where the objects to be tested within each of the management areas are inspected with the objects to be tested which are inspected, individually, on the basis of a result of the comparison in the fourth step; and a sixth step of creating the inspection schedule on the basis of the combination determined in the fifth step. - View Dependent Claims (13, 14, 15)
-
Specification