1. A computer implemented route determination system, said route determination system comprising:
- a route generator configured to define a plurality of routes on which move a material between a construction site and a destination site of a plurality of possible destination sites;
a cost scenario generator configured to determine cost scenarios associated with said plurality of routes; and
a report generator configured to generate a report which identifies said routes and said cost scenarios for said destination site.
2 Assignments
0 Petitions
Accused Products
Abstract
A computer implemented route determination system comprises a route generator, a cost scenario generator, and a report generator. The route generator is configured to define a plurality of routes on which move a material between a construction site and a destination site of a plurality of possible destination sites. The cost scenario generator is configured to determine cost scenarios associated with the plurality of routes. The report generator is configured to generate a report which identifies the routes and the cost scenarios for the destination site.
61 Citations
17 Claims
-
1. A computer implemented route determination system, said route determination system comprising:
-
a route generator configured to define a plurality of routes on which move a material between a construction site and a destination site of a plurality of possible destination sites; a cost scenario generator configured to determine cost scenarios associated with said plurality of routes; and a report generator configured to generate a report which identifies said routes and said cost scenarios for said destination site. - View Dependent Claims (2, 3, 4, 5, 6, 7)
-
-
8. A computer implemented method of determining routes from a construction site to a plurality of possible dump sites, said method comprising:
-
defining a plurality of routes on which to travel, for purposes of material dumping, from a construction site to at least one of a plurality of possible dump sites; determining cost scenarios associated with said routes; and generating a report which identifies said routes and said cost scenarios for a dump site selected from said plurality of possible dump sites. - View Dependent Claims (9, 10, 11, 12)
-
-
13. A computer implemented method of determining routes from a construction site to a plurality of possible retrieval sites, said method comprising:
-
defining a plurality of routes on which to travel, for purposes of material retrieval, from a construction site to at least one of a plurality of possible retrieval sites; determining cost scenarios associated with said routes; and generating a report which identifies said routes and said cost scenarios for a retrieval site selected from said plurality of possible retrieval sites. - View Dependent Claims (14, 15, 16, 17)
-