Systems and Methods for Integrating Demand Response with Service Restoration in an Electric Distribution System
First Claim
1. A method of restoring electrical service to a selected portion of an electric distribution system, wherein the selected portion includes at least a sub-portion of an outage area, wherein the outage area includes a fault and is not receiving an electric current from the electric distribution system, and further wherein the electric distribution system is in electrical communication with a plurality of demand responsive loads configured to be selectively isolated from the electric distribution system responsive to a load shed signal, the method comprising:
- identifying a restoration area, wherein the restoration area includes a portion of the electric distribution system that is receiving the electric current from the electric distribution system and is selectively configured to provide the electric current to the selected portion of the electric distribution system;
determining an expected fault reparation time;
forecasting an estimated electrical load within the selected portion of the electric distribution system during the expected fault reparation time;
evaluating the plurality of demand responsive loads;
selecting an isolated portion of the plurality of demand responsive loads to be isolated from the electric distribution system during at least a portion of the expected fault reparation time;
sending the load shed signal to the isolated portion of the plurality of demand responsive loads; and
providing the electric current from the restoration area to the selected portion of the electric distribution system.
5 Assignments
0 Petitions
Accused Products
Abstract
Systems and methods for integrating demand response with service restoration in an electric distribution system. The electric distribution system may include a plurality of regions, zones, and/or areas including at least an outage area that includes a fault and is not receiving electric current from the electric distribution system and a restoration area that is receiving electric current from the electric distribution system and that may be selectively configured to provide electric current to a selected portion of the outage area. The electric distribution system also includes a plurality of demand responsive loads configured to be selectively isolated from the electric distribution system responsive to a load shed signal. The demand responsive loads may be selectively utilized during service restoration, such as to provide additional excess capacity within the restoration area and/or decrease a magnitude of the electric load applied by the selected portion of the outage area.
17 Citations
26 Claims
-
1. A method of restoring electrical service to a selected portion of an electric distribution system, wherein the selected portion includes at least a sub-portion of an outage area, wherein the outage area includes a fault and is not receiving an electric current from the electric distribution system, and further wherein the electric distribution system is in electrical communication with a plurality of demand responsive loads configured to be selectively isolated from the electric distribution system responsive to a load shed signal, the method comprising:
-
identifying a restoration area, wherein the restoration area includes a portion of the electric distribution system that is receiving the electric current from the electric distribution system and is selectively configured to provide the electric current to the selected portion of the electric distribution system; determining an expected fault reparation time; forecasting an estimated electrical load within the selected portion of the electric distribution system during the expected fault reparation time; evaluating the plurality of demand responsive loads; selecting an isolated portion of the plurality of demand responsive loads to be isolated from the electric distribution system during at least a portion of the expected fault reparation time; sending the load shed signal to the isolated portion of the plurality of demand responsive loads; and providing the electric current from the restoration area to the selected portion of the electric distribution system. - View Dependent Claims (2, 3, 4, 5, 6)
-
-
7. A method of restoring electrical service to a selected portion of an electric distribution system, the method comprising:
-
forecasting an estimated electrical load within the selected portion of the electric distribution system during an expected fault reparation time; estimating an excess capacity of a restoration area; comparing the excess capacity to the estimated electrical load; evaluating a plurality of demand responsive loads, wherein the plurality of demand responsive loads is configured to be selectively isolated from the electric distribution system responsive to a load shed signal; selecting an isolated portion of the plurality of demand responsive loads to be isolated from the electric distribution system during at least a portion of the expected fault reparation time, wherein the selecting is based at least in part on at least one of the comparing and the evaluating; sending the load shed signal to the isolated portion of the plurality of demand responsive loads; and providing an electric current from the restoration area to the selected portion of the electric distribution system. - View Dependent Claims (8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26)
-
Specification