METHOD FOR THE OPERATION OF A WIND TURBINE
First Claim
1. A method of operating a wind power installation having an aerodynamic rotor with at least one rotor blade, the method comprising:
- operating the wind power installation at an operating point dependant on the wind speed;
detecting an operating parameter of the operating point;
comparing the detected operating parameter to a reference parameter; and
heating the at least one rotor blade when the detected operating parameter exceeds a threshold deviation relative to the reference parameter, while continuing the operation of the wind power installation.
1 Assignment
0 Petitions
Accused Products
Abstract
The invention relates to a method for operating a wind turbine comprising an aerodynamic rotor that has at least one rotor blade. Said method comprises the steps of operating the wind turbine at an operating point that depends on the wind speed, detecting an operating parameter of the operating point, comparing the detected operating parameter with a predetermined reference quantity, and heating the at least one rotor blade when the detected operating parameter exceeds a predetermined variation from the reference quantity, the operation of the wind turbine being continued.
23 Citations
21 Claims
-
1. A method of operating a wind power installation having an aerodynamic rotor with at least one rotor blade, the method comprising:
-
operating the wind power installation at an operating point dependant on the wind speed; detecting an operating parameter of the operating point; comparing the detected operating parameter to a reference parameter; and heating the at least one rotor blade when the detected operating parameter exceeds a threshold deviation relative to the reference parameter, while continuing the operation of the wind power installation. - View Dependent Claims (2, 3, 4, 5, 6, 19, 20, 21)
-
-
7. A rotor blade configured to be fixed to a hub of a rotor of a wind power installation, the rotor blade comprising:
-
a main portion having an end configured to be fixed to the hub; and an end portion; an air guide conduit located in the main portion and configured to deliver heated air through the main portion to the end portion. - View Dependent Claims (8, 16, 17)
-
-
9. A wind power installation comprising:
-
a rotor having at least one rotor blade that includes a main portion and an end portion, wherein the main portion includes an air guide conduit configured to deliver heated air through the main portion to an interior of the end portion; a heating device; a blower; and a control unit configured to detect an operating parameter of the wind power installation and to compare the detected operating parameter to a threshold reference parameter, the control unit configured to activate the heating device and the blower in response to the operating parameter exceeding a deviation of the threshold reference parameter and to cause heated air to blow through the air guide conduit of the main portion of the at least one rotor blade while the wind power installation is in operation. - View Dependent Claims (10, 11, 18)
-
-
12. A method of operating a wind power installation comprising an aerodynamic rotor having at least one rotor blade, the method comprising:
-
monitoring whether there is icing on the wind power installation using an ice sensor for detecting an ice accretion; and when an ice accretion is detected, heating the at least one rotor blade, while operation of the wind power installation is continued. - View Dependent Claims (14)
-
-
13. A method of operating a wind park comprising a plurality of mutually communicating wind power installations, each of the wind power installations comprising an aerodynamic rotor having at least one rotor blade, the method comprising:
-
monitoring whether there is icing on at least one of the wind power installations using an ice sensor for detecting an ice accretion; and when an ice accretion is detected, heating the at least one rotor blade of each of the wind power installations in the wind park, while operation of each of the wind power installations of the wind park is continued.
-
-
15. (canceled)