Systems and Methods for Dynamic Islanding to Minimize Load Shed During Restoration After a Fault
First Claim
1. A method of minimizing load shed during restoration after a fault in a power distribution network comprising:
- collecting customer prioritization data for a set of customers;
calculating an inconvenience factor from the customer prioritization data on each customer in the set of customers;
determining a load reduction required for restoration; and
identifying at least one zone to be isolated from the power distribution network based the load reduction and the inconvenience factor.
1 Assignment
0 Petitions
Accused Products
Abstract
A system and method for minimizing load shed during restoration after a fault in a power distribution network includes collecting customer prioritization data for a set of customers and calculating an inconvenience factor from the customer prioritization data on each customer in the set of customers. A load reduction required for restoration is determined, and at least one zone to be isolated from the power distribution network based the load reduction and the inconvenience factor is identified. The identified zone may then be isolated from the distribution network. The customer prioritization data may include customer priority data, customer load data, customer back-up device data, customer available back-up time, data related to willingness of customer to use their back-up device.
16 Citations
27 Claims
-
1. A method of minimizing load shed during restoration after a fault in a power distribution network comprising:
-
collecting customer prioritization data for a set of customers; calculating an inconvenience factor from the customer prioritization data on each customer in the set of customers; determining a load reduction required for restoration; and identifying at least one zone to be isolated from the power distribution network based the load reduction and the inconvenience factor. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9)
-
-
10. A system for minimizing load shed during restoration after a fault in a power distribution network comprising:
-
a computer; at least one subsystem that collects customer prioritization data for a set of customers; at least one subsystem that calculates an inconvenience factor from the customer prioritization data on each customer in the set of customers; at least one subsystem that determines a load reduction required for restoration; at least one subsystem that determines at least one zone to be isolated from the power distribution network based the load reduction and the inconvenience factor. - View Dependent Claims (11, 12, 13, 14, 15, 16, 17, 18)
-
-
19. Non-transitory computer readable media for instructing the determination of priorities for instructing the isolation of customers to minimize load shed during restoration after a fault in a power distribution network comprising computer readable instructions to:
-
collect customer prioritization data for a set of customers; calculate an inconvenience factor from the customer prioritization data on each customer in the set of customers; determine a load reduction required for restoration; and identify at least one zone to be isolated from the power distribution network based the load reduction and the inconvenience factor. - View Dependent Claims (20, 21, 22, 23, 24, 25, 26, 27)
-
Specification