PROVISIONING OF RESOURCES
First Claim
1. A method for reservation of resources for a service, comprising:
- receiving a request for resources for a project duration with a start time and an end time;
determining, using a processor, if the requested resources are available for the project duration;
determining a utilization level of one or more resource provisioning components during a provisioning time prior to the start time of the project;
determining if the one or more resource provisioning components have capacity to handle the provisioning of resources for the request prior to the start time of the project; and
reserving the one or more resource provisioning components for a provisioning time prior to the start time of the project.
1 Assignment
0 Petitions
Accused Products
Abstract
Reservation of resources for a service includes receiving a request for resources for a project duration with a start time and an end time; determining if the requested resources are available for the project duration; determining a utilization level of one or more resource provisioning components during a provisioning time prior to the start time of the project; and determining if the one or more resource provisioning components have capacity to handle the provisioning of resources for the request prior to the start time of the project. The one or more resource provisioning components can be reserved for a provisioning time prior to the start time of the project.
15 Citations
25 Claims
-
1. A method for reservation of resources for a service, comprising:
-
receiving a request for resources for a project duration with a start time and an end time; determining, using a processor, if the requested resources are available for the project duration; determining a utilization level of one or more resource provisioning components during a provisioning time prior to the start time of the project; determining if the one or more resource provisioning components have capacity to handle the provisioning of resources for the request prior to the start time of the project; and reserving the one or more resource provisioning components for a provisioning time prior to the start time of the project. - View Dependent Claims (2, 3, 4, 5, 6)
-
-
7-13. -13. (canceled)
-
14. A system comprising:
-
a processor programmed to initiate executable operations for reservation of resources for a service, the executable operations comprising; receiving a request for resources for a project duration with a start time and an end time; determining if the requested resources are available for the project duration; determining a utilization level of one or more resource provisioning components during a provisioning time prior to the start time of the project; determining if the one or more resource provisioning components have capacity to handle the provisioning of resources for the request prior to the start time of the project; and reserving the one or more resource provisioning components for a provisioning time prior to the start time of the project. - View Dependent Claims (15, 16, 17, 18, 19)
-
-
20. A computer program product for reservation of resources for a service, the computer program product comprising a computer readable storage medium having program code stored thereon, the program code executable by a processor to perform a method comprising:
-
receiving, using the processor, a request for resources for a project duration with a start time and an end time; determining, using the processor, if the requested resources are available for the project duration; determining, using the processor, a utilization level of one or more resource provisioning components during a provisioning time prior to the start time of the project; determining if the one or more resource provisioning components have capacity to handle the provisioning of resources for the request prior to the start time of the project using the processor; and reserving, using the processor, the one or more resource provisioning components for a provisioning time prior to the start time of the project. - View Dependent Claims (21, 22, 23, 24, 25)
-
Specification