ASPHALT RECYCLING SYSTEM AND METHOD FOR PRODUCING A NEW ASPHALT LAYER FROM THE ASPHALT TO BE RECYCLED
First Claim
1. A hot asphalt recycling system comprising a heat-insulated body with a closed volume;
- at least one RAP material transmission channel within said body, said channel being embodied so as to produce a geometrical shape with at least three edges;
a transmission line displacing within said RAP material transmission channel and comprising a plurality of transmission plates positioned thereon at certain intervals;
an outer air channel which encircles said transmission channel substantially and wherein hot air is circulated;
an accumulation reservoir which is formed inside the body and where the RAP at certain temperature is stored so as to preserve the temperature thereof; and
a discharge unit which is used to discharge the hot RAP material within the accumulation reservoir to the desired media;
in order to obtain RAC, which is to be used in the production of both of the asphalt layers (binder or bitumen base), from RAP material, characterized by comprisingan inner air channel which is positioned in the inner volume of the body, connects an air inlet pipe which provides the primary hot air input to the body to the said outer air channel and at least a section of which extends at the vicinity of the transmission line, in order to lengthen the path the hot air takes inside the body and thus in order to transfer the heat, which circulates inside the body, to the RAP in an efficient manner.a mixer wherein the RAP coming from the discharge mechanism, new bitumen at a predetermined amount and optionally at least one chemical additive are mixed for a predetermined period;
in order to produce RAC from the hot RAP, accumulated in the accumulation reservoir, as independently of an asphalt plant.
1 Assignment
0 Petitions
Accused Products
Abstract
A hot asphalt recycling system, in order to obtain RAC, which is to be used in the production of one of the asphalt layers, from RAP material, characterized by comprising an inner air channel (25) which is positioned in the inner volume of the body (20), connects an air inlet pipe (241) which provides the primary hot air input to the body (20) to the said outer air channel (24) and at least a section of which extends at the vicinity of the transmission line (23) and a mixer (50) wherein the RAP, which is at the desired amount and which comes from the discharge mechanism (27), new bitumen at a predetermined amount and optionally at least one chemical additive are mixed for a predetermined period.
9 Citations
22 Claims
-
1. A hot asphalt recycling system comprising a heat-insulated body with a closed volume;
- at least one RAP material transmission channel within said body, said channel being embodied so as to produce a geometrical shape with at least three edges;
a transmission line displacing within said RAP material transmission channel and comprising a plurality of transmission plates positioned thereon at certain intervals;
an outer air channel which encircles said transmission channel substantially and wherein hot air is circulated;
an accumulation reservoir which is formed inside the body and where the RAP at certain temperature is stored so as to preserve the temperature thereof; and
a discharge unit which is used to discharge the hot RAP material within the accumulation reservoir to the desired media;
in order to obtain RAC, which is to be used in the production of both of the asphalt layers (binder or bitumen base), from RAP material, characterized by comprisingan inner air channel which is positioned in the inner volume of the body, connects an air inlet pipe which provides the primary hot air input to the body to the said outer air channel and at least a section of which extends at the vicinity of the transmission line, in order to lengthen the path the hot air takes inside the body and thus in order to transfer the heat, which circulates inside the body, to the RAP in an efficient manner. a mixer wherein the RAP coming from the discharge mechanism, new bitumen at a predetermined amount and optionally at least one chemical additive are mixed for a predetermined period;
in order to produce RAC from the hot RAP, accumulated in the accumulation reservoir, as independently of an asphalt plant. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15)
- at least one RAP material transmission channel within said body, said channel being embodied so as to produce a geometrical shape with at least three edges;
-
16. A hot asphalt recycling method applied in order to obtain RAC, to be used in the production of one of the asphalt layers, from the RAP, characterized by comprising the steps of:
-
a) providing a body with a closed volume which is thermally and substantially insulated from the outer environment, b) advancing the RAP inside a transmission channel extending in a direction so as to define at least three corners inside said body, c) during said advancing process, circulating the hot air obtained from a hot air supply inside the inner volume of the body so as to provide heat transfer to a certain part of the RAP inside the transmission channel, d) circulating the hot air along the outer circumference of the body so as to provide heat transfer to a certain part of the RAP inside the transmission channel, e) circulating the hot air by directing the hot air inside the body so as to provide heat transfer to the RAP directly and indirectly, f) circulating the heated RAP inside the body so as to be directed to the accumulation reservoir, g) transferring the hot RAP inside the accumulation reservoir to a mixer at a predetermined arrangement, h) transferring new additional bitumen and optionally at least one chemical additive to said mixer at a predetermined arrangement, i) mixing the hot RAP material, new additional bitumen and optionally at least one chemical additive for a predetermined duration inside the mixer and discharging this mixture to the desired outer environment. - View Dependent Claims (17, 18, 19, 20, 21, 22)
-