ORE REMOVAL PRODUCTION LINE, TWIN RAMPS AND GROUND SUPPORT INSTALLATION METHOD
First Claim
1. Ore production line for a hard rock mine, wherein it comprises the following equipment, linearly and sequentially arranged between the work face of the mine and the outdoor environment:
- at least one continuous loader machine placed nearby the work face;
followed byat least one Haulage Equipment;
followed byan Ore Sizer Equipment;
followed bya Storage Buffer;
followed bya Rail-Veyor machine.
1 Assignment
0 Petitions
Accused Products
Abstract
The present invention refers to a set of methods and procedures that may be combined in order to greatly increase the speed of development of an access ramp in a underground hard-rock mine.
More particularly, the present invention was designed to target all the bottle-necks comprised by the access operation of a hard-rock mine that employs a Rail-Veyor machine.
The invention also comprises of an ore production line which consists in the sequential arrangement of a series of mining equipment between the work face and the entrance of a hard-rock mine. The invention also comprises a Hard Rock Mining Access Plan for a hard-rock mine which encompasses two parallel ramps interconnected by cross-cut passageways. Further, invention also comprises a Ground Support Installation method configured to shorten the time required for the installation of ground support inside of a hard-rock mine.
9 Citations
12 Claims
-
1. Ore production line for a hard rock mine, wherein it comprises the following equipment, linearly and sequentially arranged between the work face of the mine and the outdoor environment:
-
at least one continuous loader machine placed nearby the work face;
followed byat least one Haulage Equipment;
followed byan Ore Sizer Equipment;
followed bya Storage Buffer;
followed bya Rail-Veyor machine. - View Dependent Claims (2, 3, 4, 5, 6, 12)
-
- 7. Hard Rock Mining Access Plan for a hard-rock mine, wherein it includes two parallel ramps interconnected by a series of cross-cuts passageways, both ramps and the cross-cuts passageways being 2.9 to 3.3 meters high and 3.5 to 3.9 meters wide.
-
10. Ground Support Installation method for a hard rock mining operation, wherein it comprises two steps:
-
the first step consists of installing a minimum support required to insure the safety of the development miners and the stability of the opening for the development phase; the second step consists of installing a permanent support required to ensure the safety of the workers and the opening stability throughout the mine'"'"'s life. - View Dependent Claims (11)
-
Specification