CHANGE CONVERGENCE RISK PLANNING AND AVOIDANCE
First Claim
1. A change convergence risk mitigation system, comprising:
- a processor;
a memory;
a risk mitigation module stored in the memory, executable by the processor and configured for;
receiving information associated with a plurality of events occurring during a plurality of time periods, wherein the information associated with each event includes event timing information and event risk information;
determining an event risk score for each of the plurality of events;
aggregating the event risk scores of the plurality of events and, based on the event risk scores, determining a risk level for each of the plurality of time periods;
identifying a risk mitigation event;
based on an event risk score of the risk mitigation event, determining a risk mitigation time period from the plurality of time periods such that the risk mitigation time period would not have a predefined level if the risk mitigation event occurred during the risk mitigation time period; and
providing a recommendation that the risk mitigation event occur during the risk mitigation time period.
1 Assignment
0 Petitions
Accused Products
Abstract
Disclosed is a change convergence risk mitigation system. The change convergence risk mitigation system typically includes a processor, a memory, and a risk mitigation module stored in the memory. The change convergence risk mitigation system is typically configured for: receiving information associated with a plurality of events; determining an event risk score for each of the plurality of events; aggregating the event risk scores of the plurality of events and, based on the event risk scores, determining a risk level for each of the plurality of time periods; identifying a risk mitigation event; determining a risk mitigation time period from the plurality of time periods such that the risk mitigation time period would not have a predefined level if the risk mitigation event occurred during the risk mitigation time period; and providing a recommendation that the risk mitigation event occur during the risk mitigation time period.
-
Citations
18 Claims
-
1. A change convergence risk mitigation system, comprising:
-
a processor; a memory; a risk mitigation module stored in the memory, executable by the processor and configured for; receiving information associated with a plurality of events occurring during a plurality of time periods, wherein the information associated with each event includes event timing information and event risk information; determining an event risk score for each of the plurality of events; aggregating the event risk scores of the plurality of events and, based on the event risk scores, determining a risk level for each of the plurality of time periods; identifying a risk mitigation event; based on an event risk score of the risk mitigation event, determining a risk mitigation time period from the plurality of time periods such that the risk mitigation time period would not have a predefined level if the risk mitigation event occurred during the risk mitigation time period; and providing a recommendation that the risk mitigation event occur during the risk mitigation time period. - View Dependent Claims (2, 3, 4, 5, 6)
-
-
7. A computer program product for change convergence risk mitigation comprising a non-transitory computer-readable storage medium having computer-executable instructions for:
-
receiving information associated with a plurality of events occurring during a plurality of time periods, wherein the information associated with each event includes event timing information and event risk information; determining an event risk score for each of the plurality of events; aggregating the event risk scores of the plurality of events and, based on the event risk scores, determining a risk level for each of the plurality of time periods; identifying a risk mitigation event; based on an event risk score of the risk mitigation event, determining a risk mitigation time period from the plurality of time periods such that the risk mitigation time period would not have a predefined level if the risk mitigation event occurred during the risk mitigation time period; and providing a recommendation that the risk mitigation event occur during the risk mitigation time period. - View Dependent Claims (8, 9, 10, 11, 12)
-
-
13. A method for change convergence risk mitigation, comprising:
-
receiving, via a processor, information associated with a plurality of events occurring during a plurality of time periods, wherein the information associated with each event includes event timing information and event risk information; determining, via a processor, an event risk score for each of the plurality of events; aggregating, via a processor, the event risk scores of the plurality of events and, based on the event risk scores, determining a risk level for each of the plurality of time periods; identifying, via a processor, a risk mitigation event; based on an event risk score of the risk mitigation event, determining, via a processor, a risk mitigation time period from the plurality of time periods such that the risk mitigation time period would not have a predefined level if the risk mitigation event occurred during the risk mitigation time period; and providing, via a processor, a recommendation that the risk mitigation event occur during the risk mitigation time period. - View Dependent Claims (14, 15, 16, 17, 18)
-
Specification