Method and System for Prioritizing and Allocating Well Operating Tasks
First Claim
1. A method for managing well construction operations, comprising:
- accepting as input to a computer a list of tasks required to complete construction of at least one well, the list of tasks having at least an initial chronological order;
accepting as input to the computer measurements of at least one parameter related to at least one task on the list of tasks;
in the computer, prioritizing the list of tasks by at least one of changing at least one of a chronological order of performance and a length of time to complete at least one of the tasks based on measurements of the at least one parameter, the prioritizing performed to optimize at least one well construction performance parameter; and
displaying at least one task in the prioritized list to at least one user of the computer, or transmitting a control signal to a part of a drilling apparatus.
1 Assignment
0 Petitions
Accused Products
Abstract
A method for managing well construction operations includes accepting as input to a computer a list of tasks required to complete construction of at least one wellbore, the list of tasks having at least an initial chronological order. Measurements of at least one parameter related to at least one task on the list of tasks is entered into the computer. The list of tasks is prioritized by at least one of changing a chronological order of performance or a length of time to complete at least one of the tasks based on measurements of the at least one parameter. The prioritizing is performed to optimize at least one well construction performance parameter. The prioritized list is displayed to at least one user of the computer.
33 Citations
26 Claims
-
1. A method for managing well construction operations, comprising:
-
accepting as input to a computer a list of tasks required to complete construction of at least one well, the list of tasks having at least an initial chronological order; accepting as input to the computer measurements of at least one parameter related to at least one task on the list of tasks; in the computer, prioritizing the list of tasks by at least one of changing at least one of a chronological order of performance and a length of time to complete at least one of the tasks based on measurements of the at least one parameter, the prioritizing performed to optimize at least one well construction performance parameter; and displaying at least one task in the prioritized list to at least one user of the computer, or transmitting a control signal to a part of a drilling apparatus. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23)
-
-
24. A well construction operations management system, comprising:
-
a computer system having programmed therein a list of tasks required to complete construction of at least one well, the list of tasks having at least an initial chronological order; a sensor in signal communication with the computer system, the sensor for measuring at least one parameter related to at least one task on the list of tasks; wherein the computer system is programmed to prioritize the list of tasks by at least one of changing at least one of a chronological order of performance and a length of time to complete at least one of the tasks based on measurements of the at least one parameter, the prioritizing performed to optimize at least one well construction performance parameter; and a display device in signal communication with the computer system, wherein the computer system is programmed to display at least one task in the prioritized list to at least one user of the computer system or to transmit a control signal to a part of a drilling system. - View Dependent Claims (25, 26)
-
Specification