1. A method for performing resource management operations in a distributed computer system, the method comprising:
- analyzing resource demands of clients running in the distributed computer system to produce predicted resource demands for a specified time in the future;
changing a resource management option of a resource management analysis algorithm from a first option setting to a second option setting at a first time prior to the specified time; and
executing the resource management analysis algorithm with the second option setting in anticipation of the predicted resource demands at the specified time.
2 Assignments
0 Petitions
Accused Products
Abstract
A resource management system and method for performing resource management operations in a distributed computer system uses predicted resource demands for a specified time in the future to change a resource management option of a resource management analysis algorithm prior to the specified time so that the resource management analysis algorithm can be executed in anticipation of the predicted resource demands at the specified time.
31 Citations
24 Claims
-
1. A method for performing resource management operations in a distributed computer system, the method comprising:
-
analyzing resource demands of clients running in the distributed computer system to produce predicted resource demands for a specified time in the future; changing a resource management option of a resource management analysis algorithm from a first option setting to a second option setting at a first time prior to the specified time; and executing the resource management analysis algorithm with the second option setting in anticipation of the predicted resource demands at the specified time. - View Dependent Claims (2, 3, 4, 5, 6, 7, 8, 9)
-
-
10. A computer-readable storage medium containing program instructions for performing resource management operations in a distributed computer system, wherein execution of the program instructions by one or more processors of a computer system causes the one or more processors to perform steps comprising:
-
analyzing resource demands of clients running in the distributed computer system to produce predicted resource demands for a specified time in the future; changing a resource management option of a resource management analysis algorithm from a first option setting to a second option setting at a first time prior to the specified time; and executing the resource management analysis algorithm with the second option setting in anticipation of the predicted resource demands at the specified time. - View Dependent Claims (11, 12, 13, 14, 15, 16, 17)
-
-
18. A resource management system supported by hardware in a distributed computer system comprising:
-
an analytics engine configured to analyze resource demands of clients running in the distributed computer system to produce predicted resource demands for a specified time in the future; an option setting unit configured to change a resource management option of a resource management analysis algorithm from a first option setting to a second option setting at a first time prior to the specified time; and a resource management module configured to execute the resource management analysis algorithm with the second option setting in anticipation of the predicted resource demands at the specified time. - View Dependent Claims (19, 20, 21, 22, 23, 24)
-