1. A control device of a plant which controls operation amounts of a plurality of types of equipment constituting the plant, the control device comprising:
- a prediction model deriving unit that derives a prediction model to which a measurement value measured at the plant is input, and from which a monitoring target value which is a value to be monitored is output;
an adjustment amount calculating unit that calculates the operation amounts of a plurality of types of the equipment in a case where the monitoring target value which is to be output becomes a desired value, and calculates differences between the operation amounts of existing control and the calculated operation amounts as first adjustment amounts;
a constraint condition setting unit that sets a constraint condition of the operation amounts of a plurality of types of the equipment based on the measurement value and an operation condition of the plant when the measurement value is measured; and
an operation amount calculating unit that calculates second adjustment amounts obtained by correcting the first adjustment amounts by applying the set constraint condition for each of a plurality of types of the equipment and calculates a plurality of the adjusted operation amounts based on each of the calculated second adjustment amounts.
1 Assignment
0 Petitions
Accused Products
Abstract
A control device (70) of a plant which controls operation amounts of a plurality of types of equipment constituting the plant, the control device includes a prediction model deriving unit (71) that derives a prediction model from which a monitoring target value is output, an adjustment amount calculating unit (72) that calculates adjustment amounts of operation amounts in the case where the monitoring target value becomes a desired value and calculates differences between the operation amounts of existing control and the calculated operation amounts as first adjustment amounts, a constraint condition setting unit (73) that sets constraint conditions based on a measurement value and operation conditions of the plant 1, and an operation amount calculating unit (74) that calculates second adjustment amounts to which the constraint conditions are applied and calculates a plurality of the adjusted operation amounts based on each of the calculated second adjustment amounts.
0 Citations
9 Claims
-
1. A control device of a plant which controls operation amounts of a plurality of types of equipment constituting the plant, the control device comprising:
-
a prediction model deriving unit that derives a prediction model to which a measurement value measured at the plant is input, and from which a monitoring target value which is a value to be monitored is output; an adjustment amount calculating unit that calculates the operation amounts of a plurality of types of the equipment in a case where the monitoring target value which is to be output becomes a desired value, and calculates differences between the operation amounts of existing control and the calculated operation amounts as first adjustment amounts; a constraint condition setting unit that sets a constraint condition of the operation amounts of a plurality of types of the equipment based on the measurement value and an operation condition of the plant when the measurement value is measured; and an operation amount calculating unit that calculates second adjustment amounts obtained by correcting the first adjustment amounts by applying the set constraint condition for each of a plurality of types of the equipment and calculates a plurality of the adjusted operation amounts based on each of the calculated second adjustment amounts. - View Dependent Claims (2, 3, 4, 5, 6, 7)
-
-
8. A control method of a plant which controls operation amounts of a plurality of types of equipment constituting the plant, the control method comprising:
-
a step of deriving a prediction model to which a measurement value measured at the plant is input, and from which a monitoring target value which is a value to be monitored is output; a step of calculating the operation amounts of a plurality of types of the equipment in a case where the monitoring target value which is to be output becomes a desired value, and calculating differences between the operation amounts of existing control and the calculated operation amounts as first adjustment amounts; a step of setting a constraint condition of the operation amounts of a plurality of types of the equipment based on the measurement value and an operation condition of the plant when the measurement value is calculated; and a step of calculating second adjustment amounts obtained by correcting the first adjustment amounts by applying the set constraint condition, for each of a plurality of types of the equipment, and calculating a plurality of the adjusted operation amounts based on each of the calculated second adjustment amounts.
-
-
9. A computer-readable storage medium storing a control program of a plant which controls operation amounts of a plurality of types of equipment constituting the plant, the control program of the plant causing a computer to execute the method comprising:
-
a step of deriving a prediction model to which a measurement value measured at the plant is input, and from which a monitoring target value which is a value to be monitored is output; a step of calculating the operation amounts of a plurality of types of the equipment in a case where the monitoring target value which is to be output becomes a desired value, and calculating differences between the operation amounts of existing control and the calculated operation amounts as first adjustment amounts; a step of setting a constraint condition of the operation amounts of a plurality of types of the equipment based on the measurement value and an operation condition of the plant when the measurement value is measured; and a step of calculating second adjustment amounts obtained by correcting the first adjustment amounts by applying the set constraint condition, for each of a plurality of the equipment, and calculating a plurality of the adjusted operation amounts based on each of the calculated second adjustment amounts.
-