Method of distributing cargo
First Claim
1. A method for loading cargo into and discharging it from a plurality of mutually connected cargo spaces of unequal size, whereby to minimize the time required both for the loading operation(s) and the subsequent discharge operation(s), comprising the steps of:
- dividing the cargo to be loaded at each loading place of a series of sequentially utilized loading places into a plurality of separate portions corresponding to said plurality of cargo spaces, the quantity of the cargo portion intended for the largest cargo space(s) being the same or larger than the quantity of the cargo portion intended for any of the smaller cargo space(s), and the quantity of the cargo loaded at each loading place in said series of sequentially utilized loading places and destined for the same discharging place in a series of sequentially utilized discharging places being distributed among said separate cargo portions so that the largest cargo space(s) will have the same or a larger quantity of the cargo destined for the same discharging place as any of the smaller cargo spaces;
loading the separate portions of cargo at each loading place of said series of sequentially utilized loading places into their respective cargo spaces, with the loading in the largest cargo space(s) at each loading place being carried out at the same time as loading one or more of the other cargo spaces; and
subsequentlydischarging the separate portions of cargo destined for each discharging place of said series of sequentially utilized discharging places at the respective discharging place(s), with the discharging of cargo from the largest cargo space(s) being carried out at each discharge place at the same time as the discharging of cargo from one or more of the other cargo spaces.
0 Assignments
0 Petitions
Accused Products
Abstract
A method of distributing cargo for loading and discharging cargo spaces of unequal size based on information of the cargo volume to be loaded at each loading area and of its destination, or of an estimate of this factor which is gradually adjusted to actual values, consists in loading the same or a larger quantity of cargo in the largest cargo space or spaces as in any of the smaller cargo spaces, and placing during loading the portion of the cargo volume intended for each discharge berth in such a manner that the largest cargo spaces will contain the same or a larger quantity of cargo in this portion of the cargo volume than the smaller cargo spaces. If cargo is lacking to fill all the cargo spaces the loading is carried out in such a manner that the total cargo volume to be loaded in different cargo spaces is distributed among the cargo spaces having the nearest size, and loading and discharge is always carried out in the largest cargo spaces simultaneously with loading and discharging in one or more of the other cargo spaces.
7 Citations
1 Claim
-
1. A method for loading cargo into and discharging it from a plurality of mutually connected cargo spaces of unequal size, whereby to minimize the time required both for the loading operation(s) and the subsequent discharge operation(s), comprising the steps of:
-
dividing the cargo to be loaded at each loading place of a series of sequentially utilized loading places into a plurality of separate portions corresponding to said plurality of cargo spaces, the quantity of the cargo portion intended for the largest cargo space(s) being the same or larger than the quantity of the cargo portion intended for any of the smaller cargo space(s), and the quantity of the cargo loaded at each loading place in said series of sequentially utilized loading places and destined for the same discharging place in a series of sequentially utilized discharging places being distributed among said separate cargo portions so that the largest cargo space(s) will have the same or a larger quantity of the cargo destined for the same discharging place as any of the smaller cargo spaces; loading the separate portions of cargo at each loading place of said series of sequentially utilized loading places into their respective cargo spaces, with the loading in the largest cargo space(s) at each loading place being carried out at the same time as loading one or more of the other cargo spaces; and
subsequentlydischarging the separate portions of cargo destined for each discharging place of said series of sequentially utilized discharging places at the respective discharging place(s), with the discharging of cargo from the largest cargo space(s) being carried out at each discharge place at the same time as the discharging of cargo from one or more of the other cargo spaces.
-
Specification