Method and apparatus for peak-load coverage and stop-gap reserve in steam power plants

  • US 4,164,848 A
  • Filed: 12/21/1976
  • Issued: 08/21/1979
  • Est. Priority Date: 12/21/1976
  • Status: Expired due to Term
First Claim
Patent Images

1. An arrangement for energy storage for peak load coverage and reserve in a steam power plant, comprising:

  • live steam generator means;

    a steam turbine connected to said live steam generator means by a live steam line;

    a storage vessel with steam cushion volume and water content volume;

    a secondary steam generator with at least one stage;

    means for connecting said water content volume of said storage vessel to said secondary steam generator;

    a working steam line connecting said secondary steam generator on the steam side to said steam turbine;

    a feed water line;

    a cold water reservoir;

    a hot-water return line connecting said secondary steam generator on the water side to said feed water line and said cold water reservoir, said cold water reservoir being connected to said feed water line;

    a superheater;

    an auxiliary steam line connecting said steam cushion volume of said storage vessel to a point of the main steam cycle of the plant upstream of the entry point of said working steam line and to said live steam line following said superheater.