High speed well surveying
First Claim
1. In a borehole survey method which employs first means for measuring angular rate, and second means for sensing tilt, said second means having at least two input axes of sensitivity, said first and second means having outputs, and a rotary drive for said first and second means, the steps that include(a) operating the drive and the first and second means at a first location in the borehole, and while travel of said means lengthwise in the borehole is arrested, to determine the azimuthal direction of tilt of the borehole at such location,(b) then traveling the first and second means and the drive lengthwise of the borehole away from the first location, and operating the drive and at least one of the first and second means during such traveling to determine changes in borehole alignment which occur during traveling,(c) said (b) step including operating the drive to adjust and maintain one of said input axes horizontal during said traveling,(d) said (b) step also including integrating the output of said first means to determine changes in borehole azimuth during said traveling.
1 Assignment
0 Petitions
Accused Products
Abstract
A borehole survey method employs a first sensor for measuring angular rate, and a second sensor or sensors for sensing tilt, and a rotary drive for the first and second sensors, and includes the steps:
(a) operating the drive and the first and second sensors at a first location in the borehole to determine the azimuthal direction of tilt of the borehole at such location,
(b) then traveling the first and second sensors and the drive lengthwise of the borehole away from the location, and operating the drive and at least one of the first and second sensors during such traveling to determine changes in borehole alignment during such traveling.
51 Citations
5 Claims
-
1. In a borehole survey method which employs first means for measuring angular rate, and second means for sensing tilt, said second means having at least two input axes of sensitivity, said first and second means having outputs, and a rotary drive for said first and second means, the steps that include
(a) operating the drive and the first and second means at a first location in the borehole, and while travel of said means lengthwise in the borehole is arrested, to determine the azimuthal direction of tilt of the borehole at such location, (b) then traveling the first and second means and the drive lengthwise of the borehole away from the first location, and operating the drive and at least one of the first and second means during such traveling to determine changes in borehole alignment which occur during traveling, (c) said (b) step including operating the drive to adjust and maintain one of said input axes horizontal during said traveling, (d) said (b) step also including integrating the output of said first means to determine changes in borehole azimuth during said traveling.
-
4. In a borehole survey method which employs first means for measuring angular rate, and second means for sensing tilt, said second means having two input axes of sensitivity, said first and second means having outputs, and a rotary drive for said first and second means, the steps that include
(a) operating the drive and the first and second means at a first location in the borehole, and while travel of said means lengthwise in the borehole is arrested, to determine the azimuthal direction of tilt of the borehole at such location, (b) then traveling the first and second means and the drive lengthwise of the borehole away from the first location, and operating the drive and at least one of the first and second means during such traveling to determine changes in borehole alignment which occur during traveling, (c) said (b) step carried out to determine and maintain a horizontal direction during said travel through use of at least one of said two input axes, (d) said (b) step also including integrating the output of said first means to determine changes in borehole azimuth during said traveling.
Specification