Method of optimizing a vehicle assembly line build sequence
First Claim
1. A method of scheduling the build sequence of a plurality of objects on an assembly line in order to minimize the cost of building the objects, each object having a plurality of attributes, which together with the position of the object in the sequence, affect the overall cost of the build sequence:
- comprising the steps of;
(a) providing a computer with a representation of the object, its attributes, and a procedure for calculating the cost associated with any arrangement of the attributes,(b) generating an initial build sequence using the representation of step (a) which has a miminal cost associated with the arrangement of at least one of said attributes,(c) generating a final build sequence in accordance with a simulated annealing algorithm which utilizes a scoring function that includes the costs defined by the procedure of step (a), those costs associated with the attributes of step (b) being independently weighted in accordance with a temperature varying function,(d) providing a representation of the final build sequence usable for construction of the objects.
8 Assignments
0 Petitions
Accused Products
Abstract
A method of scheduling the building sequence of a plurality of objects on an assembly line in order to minimze the cost of building the objects is disclosed. Each object has a plurality of attributes, which together with the position of the object in the sequence, affects the overall cost of the build sequence. A computer is provided with a representation of the object, its attributes, and a procedure for calculating the cost associated with any arrangement of the attributes. An initial build sequence is generated using the representation which has a minimal cost associated with the arrangement of at least one of the attributes. A final build sequence is generated in accordance with a simulated annealing algorithm which utilizes a scoring function that includes the costs defined by the procedure, those costs associated with the attributes being independently weighted in accordance with a temperature varying function. A representation of the final build sequence usable for construction of the object is then provided.
-
Citations
5 Claims
-
1. A method of scheduling the build sequence of a plurality of objects on an assembly line in order to minimize the cost of building the objects, each object having a plurality of attributes, which together with the position of the object in the sequence, affect the overall cost of the build sequence:
comprising the steps of; (a) providing a computer with a representation of the object, its attributes, and a procedure for calculating the cost associated with any arrangement of the attributes, (b) generating an initial build sequence using the representation of step (a) which has a miminal cost associated with the arrangement of at least one of said attributes, (c) generating a final build sequence in accordance with a simulated annealing algorithm which utilizes a scoring function that includes the costs defined by the procedure of step (a), those costs associated with the attributes of step (b) being independently weighted in accordance with a temperature varying function, (d) providing a representation of the final build sequence usable for construction of the objects.
-
2. A method of scheduling the build sequence of a plurality of vehicles on an assembly line in order to minimize the cost of building the vehicles, each vehicle having a plurality of attributes, which together with the position of the vehicle in the sequence, affect the overall cost of the build sequence:
comprising the steps of; (a) providing a computer with a representation of the vehicle, its attributes, and a procedure for calculating the cost associated with any arrangement of the attributes, (b) generating an initial build sequence using the representation of step (a) which has a miminal cost associated with the arrangement of at least one of said attributes, (c) generating a final build sequence in accordance with a simulated annealing algorithm which utilizes a scoring function that includes the costs defined by the procedure of step (a), those costs associated with the attributes of step (b) being independently weighted in accordance with a temperature varying function, (d) providing a representation of the final build sequence usable for construction of the vehicles.
-
3. A method of scheduling the build sequence of a plurality of vehicles on an assembly line in order to minimize the cost of building the vehicles, each vehicle having a plurality of attributes, one of which is color, which together with the position of the vehicle in the sequence, affect the overall cost of the build sequence:
comprising the steps of; (a) providing a computer with a representation of the vehicle, its attributes, and a procedure for calculating the cost associated with any arrangement of the attributes, (b) generating an initial build sequence using the representation of step (a) which has a miminal cost associated with placing the color attribute, (c) generating a final build sequence in accordance with a simulated annealing algorithm which utilizes a scoring function that includes the costs defined by the procedure of step (a), those costs associated with the attribute color being independently weighted in accordance with a temperature varying function, (d) providing a representation of the final build sequence usable for construction of the vehicles.
-
4. A method of scheduling the build sequence of a plurality of objects in order to minimize the cost of building the objects, each object having a plurality of attributes, which together with the position of the object in the sequence, affect the overall cost of the build sequence:
comprising the steps of; (a) providing a computer with a representation of the object including its attributes, and a procedure for calculating the cost associated with any arrangement of the attributes, (b) generating an initial build sequence using the representation of step (a) which has a minimal cost associated with the arrangement of at least one of said attributes, (c) generating a final build sequence in accordance with a simulated annealing algorithm which utilizes a scoring function that includes the costs defined by the procedure of step (a), those costs associated with the attributes of step (b) being independently weighted in accordance with a temperature varying function, (d) providing a representation of the final build sequence usable for construction of the objects.
-
5. A method of scheduling the build route of a plurality of components in an assembly plant in order to minimize the cost of building the components, each component having a plurality of attributes, which together with the position of the component in the route, affect the overall cost of the build route:
comprising the steps of; (a) providing a computer with a representation of the component including its attributes, and a procedure for calculating the cost associated with any arrangement of the attributes, (b) generating an initial build route using the representation of step (a) which has a minimal cost associated with the arrangement of at least one of said attributes, (c) generating a final build route in accordance with a simulated annealing algorithm which utilizes a scoring function that includes the costs defined by the procedure of step (a), those costs associated with the attributes of step (b) being independently weighted in accordance with a temperature varying function, (d) providing a representation of the final build route usable for construction of the components.